How Project Managers Can Execute Force Majeure Clauses

From the Voices on Project Management Blog
by , , , , , , , , , , , , , , ,
Voices on Project Management offers insights, tips, advice and personal stories from project managers in different regions and industries. The goal is to get you thinking, and spark a discussion. So, if you read something that you agree with - or even disagree with - leave a comment.

About this Blog

RSS

View Posts By:

Cameron McGaughy
Marian Haus
Lynda Bourne
Lung-Hung Chou
Bernadine Douglas
Kevin Korterud
Conrado Morlan
Peter Tarhanidis
Mario Trentim
Jen Skrabak
David Wakeman
Roberto Toledo
Cecilia Wong
Vivek Prakash
Cyndee Miller
Shobhna Raghupathy

Recent Posts

Level 5 Leadership: Taking Your Project from Good to Great

Sprinting a Marathon

How Managers Can Grow Into Leaders

Managing The Last 100 Feet

The Network Diagram Mentality

Email Notifications off: Turn on

Categories: Best Practices


The revolutions and demonstrations last year in the Middle East and North Africa, dubbed the Arab Spring of 2011, was a trying time for project managers in the region. As we near the first year anniversary of these historic events, we face more uncertainty.

We have witnessed the evacuation of expatriate staff, the relocation of operations, and an unmotivated local workforce. Project managers still see strikes, riots, civil disobedience and tension.  

Some projects have been derailed, failed to meet their objectives or are late. Customers have faced contractors, suppliers and developers absolving themselves of their contractual responsibilities by pleading "force majeure."

"Force majeure" is a common contractual clause that frees parties, bound by a contract, from liability or obligation if an "act of god" happens. Unless these acts are clearly defined, they are assumed to be extraordinary events with an extremely low likelihood of occurring.  

If used, force majeure clauses shift risk allocation from project contractors to their customers or other contractual stakeholders.

Organizations with projects in regions where force majeure events have taken place should prepare for ongoing conditions. To reduce the potential for conflict and ambiguity, organizations should add more contractual detail and definition to force majeure provisions in existing and new contracts. It eases tension and increases the prospect of sharing the responsibilities of cost and impact from these events.

Project managers can follow these good practices to add detail and definition to force majeure clauses in the following way:

Define what circumstances and events constitute a force majeure.

What constitutes force majeure in my region seems to be open to interpretation. My advice to project professionals is to provide as much clarity to this clause as feasibly possible by listing examples and inclusions.

Depending on the project's nature and location, the list might highlight political unrest, riot, war, invasion, terrorism, civil war, rebellion, revolution or insurrection. Other events could be radiation leaks, nuclear accidents, toxic explosions and natural disasters.

Define what constitutes the end of a force majeure.

A demonstration or strike would have a start and end time, for example. However, this event may have ongoing implications that could disrupt project work. This may include changed work conditions, reduced resource and productivity, or loss of utilities, materials and equipment.

The force majeure clause should detail whether these impacts are the reasons for non-performance and non-liability for damages.

Agree on a formal process in the event of a force majeure.

There should be additions to the clause on:

  • Formal notice time
  • Method of notification of a force majeure event
  • Process for executing mitigation responses
  • Agreement on a neutral country where arbitration can be held
Identify risk planning and mitigation responsibilities.

Project managers should identify risks and responses associated with continuing the project work such as:

  • Renegotiation of contracts reflecting any changes or cost increases in the market
  • Force majeure insurances, associated guarantees and contingency funds
  • Clarity on when to reasonably employ mitigation responsibilities, the costs and time period of mitigation efforts, and whether these efforts should be shared or incurred and for how long
  • Revision of schedules or extensions for projects with fixed completion dates
  • Recovery of agreed costs  
  • Eventual termination of the contract
What advice can you give project managers in force majeure situations?

Read more posts from Saira.
Posted by Saira Karim on: March 01, 2012 11:17 AM | Permalink

Comments

Jacky Peng
I learned from this article to understand the importance of force majeure for a project.

We need to identify any risks of circumstance and event, and consider them to define into force majeure clauses for continuing the project work.

Ralf
Force Majeure or not - some of the countries in the Middle East look tense and in tough shape. I requires high due diligence on the part of the key project stakeholders to avert major issues more than anything.


saira
Thanks Ralf, you're absolutely right, a high level of due diligence is required and part of that may be looking back at contracts and clauses in order to protect the projects interests.

Thanks Jacky, I wanted to draw attention to this clause as it often gets brushed over. But when suppliers and contractors decide to use it the impact to the project can be huge.