I think it's an interesting topic, in Agile where project scope is flexible and a lot of things can change, I would say that your burndown and burnup charts data (for product backlog) comparing with burnup and burndown sprint charts data could give you some metrics. If you figure out which data can be used, you can calculate EV. Important thing would be to compare burnt story points to the current backlog story points not to the one created initially (as scope is not fixed).