How pull future PV values from MS Project?

linkedin twitter facebook  
avatar
E Werner La Jolla, Ca, United States
I want to create a dashboard chart showing the typical PV, EV, and AC. However I'd like to show the entirety of PV, including PV for future dates all the way to the Go Live milestone. Any idea how to get future PV by period out of MS Project?

Thanks,
Erik
avatar
Gary Harvey VP Technical Services| Pinnacle Vienna, Va, United States
Erik - go to the Resource Usage view. You can right click in the spreadsheet area to adjust the values being shown.