Essentials of Successful Project Schedule Planning: Part I

From the Voices on Project Management Blog
by , , , , , , , , , , , , , , , , , ,
Voices on Project Management offers insights, tips, advice and personal stories from project managers in different regions and industries. The goal is to get you thinking, and spark a discussion. So, if you read something that you agree with--or even disagree with--leave a comment.

About this Blog

RSS

View Posts By:

Cameron McGaughy
Lynda Bourne
Kevin Korterud
Conrado Morlan
Peter Tarhanidis
Mario Trentim
Jen Skrabak
David Wakeman
Wanda Curlee
Christian Bisson
Yasmina Khelifi
Sree Rao
Lenka Pincot
Soma Bhattacharya
Emily Luijbregts
cyndee miller
Jorge Martin Valdes Garciatorres
Marat Oyvetsky
Ramiro Rodrigues

Past Contributors:

Rex Holmlin
Vivek Prakash
Dan Goldfischer
Linda Agyapong
Jim De Piante
Siti Hajar Abdul Hamid
Bernadine Douglas
Michael Hatfield
Deanna Landers
Kelley Hunsberger
Taralyn Frasqueri-Molina
Alfonso Bucero Torres
Marian Haus
Shobhna Raghupathy
Peter Taylor
Joanna Newman
Saira Karim
Jess Tayel
Lung-Hung Chou
Rebecca Braglio
Roberto Toledo
Geoff Mattie

Recent Posts

Is Planning Predictive or Persuasive?

5 Ways to Up Your Mentorship Game

Lessons Learned on Digital Transformation

Murphy's Law: It’s a Call to Action, Not an Excuse

Emergent Strategy: How To Lead Now


Categories: Project Planning


Technically speaking, the project schedule is a key project planning component. But practically speaking, simply creating a project schedule does not guarantee project success. Project success requires the project manager to plan out a reliable, comprehensive and realistic schedule.

The following three-pronged approach helps in creating such a schedule: set up a schedule planning framework, master schedule basics and run the project avoiding the classic schedule planning pitfalls.

In this post, I will shed some light on a simple schedule planning framework. Effective schedule planning boils down to five basic steps: 

  1. Plan. Identify which sources and resources will provide the project schedule information, such as the scope baseline, scheduling takeaways from similar previous projects and subject matter experts. Select the appropriate software tool to manage the schedule. This could be a standard project management tool used by your company, or it can be one you have selected considering your project's level of complexity, reporting automation needs and team collaboration requirements.
  2. Develop. Break down the work packages and deliverables into actionable tasks. Identify key milestones, such as completion of major deliverables or project phases. Sequence tasks logically, depending on their execution order and dependency on other tasks. Match team members to each task with their corresponding skills. Assess task efforts and all project time based on historical data from a similar project, or using techniques such as the Program Evaluation and Review Technique (PERT).
  3. Validate. Work with subject matter experts to review and validate the developing schedule.
  4. Follow through. After creating a baseline project schedule, track the completed tasks and achieved milestones. Developing a project schedule is not a final destination -- it has to be maintained.
  5. Adjust. You will rarely finish the project by following the exact schedule plan you began with. Adjust the schedule as you go by exploiting the opportunities that arise (such as fast-tracking activities or finishing work earlier, if possible), or taking corrective actions when faced with delays or unexpected activities (such as enlarging the team or "crashing" activities).

What are your must-do steps when creating a project schedule? What scheduling framework has been successful for you?

Posted by Marian Haus on: April 10, 2013 11:13 PM | Permalink

Comments (8)

Please login or join to subscribe to this item
Thanks for sharing...


Thanks for sharing.
Unfortunately, most of the rookies think that schedule development is the only thing that should be done for the successful planning

I like it. In general terms, is a good proposal that must be tropicalized for each organization, depth of detail according to the type of project and contract, as well as the maturity that the organization has in project management...

I would add a key step as part of Validation, that is Team Buy-in. It is important every team member own their piece of the integrated schedule and develop next level tasks to achieve the schedule. I always stress on one thing to my team, Scheduler is a facilitator he dont own the schedule. It is responsibility of the individual team member to provide the right inputs and own the schedule.

I do believe that the role of Project Scheduling is essential and even critical.

Best scheduling practice will lead your project to the success.

Schedule always provide the major focus area to the Project Manager...i.e. Activity on the critical path, resource availability, budget/cost performance or variance / Project delays...

But I would like to say that It's not the Project Management....it's a part of Project Management...

I do believe that for the successful completion of your project... roles and responsibility of every individual stakeholder are more important...

Thanks for the article

Thanks for sharing.

Best scheduling practice will lead to project success