Certification Insider

by
Cornelius Fichtner help you with your PMP Exam Prep (https://www.project-management-prepcast.com) as well as earn free PDUs (www.pm-podcast.com/pdu). Passing the PMP Exam is tough, but keeping your PMP Certification alive is just as challenging. Preparing for the exam requires an in-depth study of the PMBOK Guide and dedicated study discipline. And once you are PMP certified, then you are required to earn 60 Professional Development Units (PDUs) every 3 years to keep your certification alive. Let me help you make this journey easier with tips and tricks on how to prepare for and pass the exam as well as efficiently earning your PDUs once you are certified.

About this Blog

RSS

Recent Posts

Episode 408: How to Write Excellent User Stories

Episode 407: The Agile Practice Guide

Episode 406: Leading Projects Without Authority

Episode 405.2: The PMI-ACP Exam is Changing in 2018

Episode 405.1: The PMP Exam is Changing in 2018

Sample PMP Exam Questions for Free. No need for sign-up!

PMP exam sample questionTest your PMP knowledge right now with this 8th Set of 15 free PMP Exam sample questions in an online exam:

http://free.pm-exam-simulator.com/index.php/free-eight

This exam is just one of a series of 8 exams. To sign up for all our free exams please visit http://www.free-pm-exam-questions.com/

Don't let this chance pass by. Practice always makes perfect!

 

Posted on: February 13, 2014 08:47 AM | Permalink | Comments (0)

Free PMP Exam Sample Question

PMP Exam Q and A

The following PMP® exam sample question is taken from the Free PMP Exam Simulator. (The answer is at the very bottom):

You are managing a software development project. In the middle of the project, you find out that you are way behind schedule. Your company has invested a lot in this project, and if you don't deliver the project on time, it will be a total disaster. You analyze your project schedule to adjust it so that you may be able to complete the project on time with the existing resources. You find out that you have a lot of discretionary dependencies in your project schedule. What is the best way for you to adjust the project schedule so that you may be able to complete the project on time?

A) Keep the discretionary dependencies intact and apply Crashing    
B) Keep the discretionary dependencies intact and apply Fast Tracking    
C) Remove the discretionary dependencies and apply Crashing    
D) Remove the discretionary dependencies and apply Fast Tracking

Hint:

You need to find a way out of this problem with your existing resources.

Answer and Explanation:

The Correct Answer is D. As you need to find a way out of this problem with your existing resources, you can't apply the Crashing technique. You can only apply Fast Tracking after removing the discretionary dependencies from the project.

*All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Posted on: February 02, 2014 06:55 PM | Permalink | Comments (0)

Take a free sample PMP exam. No signup required

Practice makes perfect, so test your PMP knowledge right now with the following 15 free PMP Exam sample questions in an online exam:

http://free.pm-exam-simulator.com/index.php/sechsgratis

This exam is just one of a series of 8 exams. To sign up for all our free exams please visit http://www.free-pm-exam-questions.com/
 

Posted on: January 08, 2014 02:50 AM | Permalink | Comments (0)

Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator (The answer is at the very bottom):



 

Which of the following statements regarding the WBS is incorrect?

A) The WBS subdivides project work into smaller and more manageable components    
B) The WBS is a deliverable-oriented hierarchical decomposition of the project work    
C) The WBS organizes and defines the total scope of the project    
D) The components of the WBS are called work packages

 

 Hint: All of the choices look true but one of them is a trick.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

 

Answer and Explanation:

The Correct answer is D. "The WBS can contain components at many levels. The planned work contained within the lowest levels of the WBS components are called work packages. The work package level is ONLY at the lowest level in the WBS. Items at the other levels of the WBS are simply called ""WBS components"".
We were looking for the INCORRECT statement among the four answers. The statement that ""The components of a WBS are called work packages."" suggests that ALL the components are called work packages. This is incorrect because (as explained above) only the lowest level contains the work packages."

Posted on: December 19, 2013 11:18 PM | Permalink | Comments (1)

Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator (The answer is at the very bottom):

You are managing an electric works project. You are required to design and deploy the electrical network for an airport construction project that is underway. Your project is part of the airport construction program your company is undertaking. A number of other sub-projects, such as building and runway construction, and communication network deployment are part of the program. Due to the inter-project dependencies, your sponsor always seems panicked and in a hurry to do everything. Which of the following classification models should you choose to analyze the impact of your project sponsor as a stakeholder?

A) Power/Interest Grid    
B) Power/Influence Grid    
C) Influence/Impact Grid    
D) Salience Model

 

Hint:

This model analyzes stakeholders based on their power and urgency.  

 

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

 

Answer and Explanation:

The Correct answer is D. The Salience Model analyzes stakeholders based on their power (ability to impose their will), urgency (need for immediate attention), and legitimacy (their involvement is appropriate).