Planning: The Efficiency Zone

Planning: The Efficiency Zone

Categories: Planning

Yogi Berra was fond of saying “If you don’t know where you are going, you’ll end up someplace else.”  What Yogi was getting at was that it’s a good idea to do a bit of thinking, a bit of planning, before you get started.  In the previous blog, Planning: When Have you Done Enough? we explored the factors that affect how much planning we should do.  The challenge is that the factors are qualitative in nature, requiring us to make a decision that is based on intuition.  

In this blog we explore how to increase the chance that we get as close as we can to achieving the maximum value from our planning efforts.  The following figure is organized into four planning quadrants, each one of which represents a target area for our planning efforts.  

Figure – The four quadrants of planning efficiency.

Planning quadrants

Let’s explore each quadrant.  In order from most desirable, to least desirable, they are:

  1. Q1: Efficient. The most efficient approach is to do a bit less planning than is sufficient, to undershoot the mark.  The idea is that you want to get close to sufficient and be prepared to explore the aspects of your plan later in the lifecycle when you discover that it’s insufficient.  This strategy assumes you have easy access to the subject matter experts (SMEs) and decision makers, thereby enabling you to quickly adjust and evolve your plan as needed.
  2. Q2: Comfortable. Some people will aim for this quadrant out of the believe that they need to think everything through right now, that they won’t be allowed to update the plan easily later on in the lifecycle.  Although this is comfortable for people who are new to Disciplined Agile (DA) ways of working (WoW) it is also wasteful because they’ve invested too much on the planning effort.
  3. Q3: Insufficient. This is where a lot of agile purists, or non-managers who are new to agile, end up. When planning is grossly insufficient like this your team tends to work in an undirected manner that results in a lot of rework later.
  4. Q4: Wasteful. This is where a lot of traditional managers who are new to agile WoW land. This strategy is particularly problematic in areas where there is great uncertainty, in particular software development where requirements and underlying technologies change rapidly.  Planning efforts that land in quadrant 4 are often caused by impedance mismatch between the expectations of the people doing the planning, or the expectations of the people who require a detailed plan before the rest of the work commences, and the reality of the situation on the ground.  Very often the environment has changed but the planning methodology hasn’t, so lighten up.

Eisenhower said “Plans are worthless, but planning is everything.” There can be significant value in planning, but it is possible to go too far, to plan too much.  Although more research is needed in this space, it appears that the value of planning follows the law of diminishing returns – there is significant value in doing some planning, but that value quickly reaches a maximum point. Determining that maximum point is a qualitative, “gut feel” decision based on a collection of factors such as the complexity and risk of the situation, the skills and experience of the people involved, and the uncertainty that you face.  Surprisingly, the most efficient approach to planning is to aim for your plans to be slightly insufficient, to be close but in need of a bit more work when you discover that you need to work through a few more details.  I hope this blog series has been food for thought.
 

Posted on: November 19, 2019 06:39 AM | Permalink | Comments (14)

Planning: When Have We Done Enough?

Categories: Planning

In the previous blog we examined what the value of planning is, so that we can then determine how much planning we need to do.  The answer to this question was “it depends,” and the implication was that we need to do just enough planning for the situation that we face and no more.  In this blog we go deeper to explore what this depends on in practice.

We learned in the previous blog that our planning efforts should be sufficient, what we referred to as just barely good enough (JBGE) in Agile Modeling, for the situation that we face.  The following figure depicts the contextual factors that we should consider, with the factors motivating us to do more planning on the left-hand side under the red arrow and the factors enabling us to do less planning on the right-hand side under the green arrow.  These factors are mostly qualitative in nature, implying that it requires a judgement call on the part of the people involved with the planning effort to determine whether they’ve planned sufficiently. Let’s explore each of these factors in more detail.

Figure. The factors to determine whether you’ve planned sufficiently.

There are four factors that motivate us to increase the amount of planning we do:

  1. Risk. The greater the risk that we face the more we will want to think before we act.  For example, transporting perishable medical supplies from Toronto to Timbuktu requires more logistical planning than transporting a box of Choose Your WoW! books from Toronto to Philadelphia.
  2. Domain complexity.  The more complex the problem that we’re trying to solve, the more we want to invest in exploring the domain and then thinking through how we will address the complexity.  For example, building a bridge across a river is more complex than building a dog house, so we will invest more time thinking through the building of the bridge.
  3. Solution complexity. The greater the complexity of the solution that we are building, or configuring in some cases, the more thinking we will need to do.  For example, installing an ERP system into an existing organization to replace dozens of legacy systems requires more planning than installing a new app on your phone.
  4. Desire for “predictability.” This can be a common cultural challenge within organizations, in particular the desire to be told up front how much a project will cost or how long a project will take.  These are fairly reasonable requests when the endeavor is something our team has experience in doing, such as a house builder being asked to build a new house. They are unreasonable requests when the team is being tasked with doing something that is ill-defined or whose scope will change throughout the endeavor, the situation typically faced by software development teams.  Far too many times I’ve seen teams run aground due to an unrealistic request for predictability – the teams will overly invest in up-front modeling and planning, will then make promises regarding cost and schedule that either they’re unable to keep or can only keep by cutting scope or quality of the delivered solution.

There are six factors that enable us to reduce the amount of planning that we need to do:

  1. Skill.  The greater the skill of the people doing the work, the less planning will be required for that work. 
  2. Experience.  The greater the experience of the people doing the work, the less planning will be required for that work.
  3. Ease of change. The easier it is to change the work products being produced, including the solution itself, the less planning is required.  For example, we are developing a website it is relatively easy to update and then redeploy web pages if we discover that they need to evolve.  So we can get away with minimal planning.  Conversely, if we are building a bridge spanning a river it is relatively difficult and expensive to rebuild a supporting pillar in the middle of the river if we discover that it was placed in the wrong spot. In this case we face greater deployment risk so we need to invest in greater planning to increase the chance of getting things right.
  4. Access to stakeholders.  The easier it is to access stakeholders, in particular decision makers who can provide direction and feedback to us, in general the less initial planning we need to do.  Being able to work closely with stakeholders enables us to think through the details when it’s most appropriate during a project, not just up front.
  5. Communication and collaboration. The greater the communication and collaboration within a team, perhaps because we’re co-located in a single room or because we are using sophisticated communication software, the less planning is required due to the increased opportunities for streamlined coordination. 
  6. Uncertainty. The more likely that something will change the less planning you should do because when it does change your planning efforts around it will have been for naught. 

To summarize, the answer to “when have we planned sufficiently?” is “it depends.”  In this blog we explored several factors that motivate you to increase the amount of planning we need to do and several factors that enable us to reduce the amount of planning.  In effect we went beyond the typical consultant answer of “it depends” to the more robust answer of “it depends on this.”  

In the next blog in this 3-part series we explore how to be efficient in our planning efforts. I suspect the answer it won’t be what you’re expecting.

Posted on: November 04, 2019 09:42 AM | Permalink | Comments (12)

Planning: How Valuable is it?

Categories: Planning

Winston Churchill once said “Plans are of little importance, but planning is essential.” What Churchill meant was that the value is in thinking something through, in planning it, before you do it. So this leads to some interesting questions: How much planning should we do?  How can we get the most value out of our planning efforts? I wish I could tell you that there is solid research evidence to answer this question but sadly I haven’t been able to find any (if you know of any, I’d love to hear about it). Luckily though, we do have a lot of experience and observational evidence to fall back on.

From an accounting point of view we know that value is calculated as benefit minus cost. The implication is that all we need to do then is calculate the benefits of planning, and the costs of doing so, apply a bit of math and there you go.  How hard could that be? As we know it’s very difficult to calculate the benefits because some are qualitative, requiring a bit of creativity to turn them into a monetary figure. The bigger challenge is that planning is just one activity of many that go into achieving a benefit making it difficult to tease out the planning portion of the benefit earned. Calculating the true costs of planning isn’t much easier when you start to consider the downstream implications of the work required to gather the inputs that go into the planning process.  This is a particular problem in creative domains such as software development, more in this in future blogs.  The implication is that in practice there isn’t an easy way to determine the actual value of planning, which explains the dearth of research evidence around this issue.  

Because there are no hard and fast rules to determine the value of planning, practitioners rely on belief systems to guide their thinking.  Figure 1 overviews two common belief systems, the traditional (sometimes inappropriately called “predictive”) belief system and the agile belief system.  We’ve labelled the latter as undisciplined because we will distinguish this from a Disciplined Agile (DA) strategy later.  The traditional belief system tells us that the more effort that you put into planning the more value that you will gain from doing so.  This belief system tells you to think things through in detail before you do them.  This increases value by avoiding mistakes in the future, thereby reducing costs. At the other extreme the (undisciplined) agile belief system tells us that there is very little value in planning, that you are better advised in focusing on being able to react to feedback.  This enables you to deliver sooner and thereby earn the actual benefits sooner and longer, thereby increasing value.  The obvious downside of course is that mistakes will be made, sometimes serious ones, thereby increasing both costs and risks. 

Figure 1. What our belief systems tell us about the value of planning.

The methodologist in me tells me that extremes are generally a bad thing, that for most situations the answer lies somewhere in between.  The easy answer would be to simply draw a dashed line in between the two curves in Figure 1, or get really fancy and introduce some sort of range between the two lines, but the easy answer is wrong.   What we really need to do is look at what actually happens in practice, something that we did in the Agile Modeling (AM) community in the early 2000s.

In AM we needed to determine the value of modeling so as to provide coherent advice around when to model and to what extent to model. To make a long story short, we observed that the value of modeling followed the law of diminishing returns as you can see in Figure 2.  A little bit of modeling offered a lot of value.  So did a bit more, then a bit more, then a bit more.  But very quickly we reach a point of diminishing returns, the total costs of modeling soon exceeds the total benefits of modeling – once a model is sufficient for the situation that you’re thinking through with it, you reach a point where any more modeling removes overall value.  This point is what we called the just barely good enough (JBGE) point, although others prefer “sufficient” as a term.  So why am I talking about the value of modeling? Because modeling and planning are slightly different flavors of the same thing: Thinking something through before you jumping into doing it.

Figure 2. The value of planning/modeling.

 

JBGE?  What?

Many people, particularly those who follow a traditional “predictive” lifecycle approach, tend to be taken aback when they’re told the most effective plans are those that are just barely good enough.  The problem is that they often interpret JBGE as insufficient, yet by definition that is clearly not the case.  If your planning efforts haven’t been sufficient then you can still benefit from more planning, or to be accurate you can benefit from good planning at the right time.  But, if your planning efforts have been sufficient, or more than sufficient, then more planning is only going to remove value.  From a lean point of view over-planning is a waste.  

To summarize, the DA belief system is that the value of planning and modeling follows the law of diminishing returns. There is significant anecdotal evidence that bears this out but as I indicated earlier the research evidence is sparse.  I’ve actively prodded researchers along when I could for the past 15 years to get this evidence, but these efforts have always floundered when they discovered that this research is very difficult long-term work.  

In the next blog in this 3-part series we explore how to determine when your planning efforts are sufficient.  Following that we work through how to be efficient at planning.

 

Posted on: October 24, 2019 11:59 PM | Permalink | Comments (16)