Risk response strategy for Residual risk
Network:1504



When is separate Risk response strategy required for Residual Risk?
Sort By:
Page: 1 2 next>
Network:26



no, because they remain after risk response was already implemented, and are usually accepted
Network:1106



Residual risk, by default, has the separate risk response strategy of acceptance. So we could have taken a transfer, mitigate or avoid response with a particular negative risk and whatever risk exposure remains after is accepted.

Kiron
Network:102949



I totally agree with Kiron and can't add more to that. Those risks for sure has a separate response strategy to address them should they occur.
Network:323



As Kiron said, the residual risk is coming after risk response implement as per shown in project documents update then it will be updated in risk register and go to procees planning again as per PMBOK!!!
Network:26



After risk response strategy was implemented there could be two types of risks - residual and secondary. Residual are expected/known and should have been considered in the initial strategy but secondary risks will require new strategy.
Network:14377



I agree with Rajesh, but he isn't here! ;-)
...
1 reply by Rami Kaibni
Aug 29, 2018 10:17 AM
Rami Kaibni
...
Good One :-)
Network:102949



Aug 29, 2018 6:29 AM
Replying to Sante Vergini
...
I agree with Rajesh, but he isn't here! ;-)
Good One :-)
Network:1504



Thanks, everyone for the explanation

Hi Petar,
Residual Risks are those risks which remain after the planned responses of risk have been taken and Secondary Risks are those risks which arise as a direct result of implementing a risk Response

Hence Risk response strategy will only prepare for the new risk (Secondary Risks) and not for Residual Risks that is as per PMBOK but what is the good practice in the real project?

Is there follow the same ??
Network:106900



Moloy,

You should review the impact of risk response on regular basis. Progress in the project may add or remove risk, and your risk response may impact differently over time. creating new residual risk or secondary risk.
Network:26



I don't think there could be definite answer about the residual risks. It may be depends on the project type, industry, complexity, etc.
In my projects, residual risks are accepted with allocated contingency reserve, and have low impact and probability, and I don't do anything more due to resource constraints :-(
A good practice is may be to review them from time to time but this always depends on the resources PM has available to handle risks :-)
Page: 1 2 next>  

Please login or join to reply

Content ID:
ADVERTISEMENTS

"There is one way to find out if a man is honest: Ask him! If he says yes, you know he's crooked."

- Groucho Marx

ADVERTISEMENT

Sponsors

Vendor Events

See all Vendor Events