Is there a deliverable called risk response plan?
Network:0

Is there a deliverable called risk response plan?
Which document should we refer to find out the risk response to be implemented?
Sort By:
Network:1882



In my personal experience we use the risk register to put the response plan inside it. Obviously the risk response plan could generate other documents and in fact a parallel project too.
Network:655



As per PMBOK, the risk register should contain risk response list
Network:1572



Deepa -

Basic risk responses are captured in the risk register but the "footprint" of a risk response might be seen in many other PM documents including the WBS & schedule or budget.

Kiron