Agile Practice Management and Earned Value Management Methods.
Network:125



To all my colleagues in the fields of Project Management, Agile practice development and management as well as Earned Value Management(EVM) I want your feedback on the following questions;

1. How many of you are successfully using EVM methods to measure business value back to an organization using Agile methods for projects?

2. If you are using EVM in your implementation of Agile are you willing to share how your demonstrating business value through this method?

Comments and feedback welcome.

#businessvalue #projectmanagement #earnedvaluemanagement #measurements
#kanban #scrum
Sort By:
Network:2105



We use EVM in our shop. Our approach is more of a hybrid, as we are a vendor working with clients in systems implementations for business transformations. In order to scope and budget the project we exercise some upfront planning, then drive the work through a scrum-like approach.

Since we have a budget and overall schedule, we can use standard EVM. Project numbers are reported out of our ERP and presented via Excel dashboard with built-in formulas.
...
1 reply by Martin Talbott
Feb 20, 2019 4:42 PM
Martin Talbott
...
Thank you Andrew and Rajesh for your feedback.
Network:6781



We use EVM in our Development environment. It is inbuilt into our Planning/tracking templates of MPP. EVM measures are reported to Higher Management periodically.
Network:125



Feb 17, 2019 9:14 PM
Replying to Andrew Craig
...
We use EVM in our shop. Our approach is more of a hybrid, as we are a vendor working with clients in systems implementations for business transformations. In order to scope and budget the project we exercise some upfront planning, then drive the work through a scrum-like approach.

Since we have a budget and overall schedule, we can use standard EVM. Project numbers are reported out of our ERP and presented via Excel dashboard with built-in formulas.
Thank you Andrew and Rajesh for your feedback.
Network:125



I have also built a excel spreadsheet to track EV ON OUR agile projects as well.

Please login or join to reply

Content ID:
ADVERTISEMENTS

"Impartial observers from other planets would consider ours an utterly bizarre enclave if it were populated by birds, defined as flying animals, that nevertheless rarely or never actually flew. They would also be perplexed if they encountered in our seas, lakes, rivers and ponds, creatures defined as swimmers that never did any swimming. But they would be even more surprised to encounter a species defined as a thinking animal if, in fact, the creature very rarely indulged in actual thinking."