Hello Alvaro,
According to the PMBOK Fifth edition, here the order: 1. Confirm work is done to requirements 2. Complete procurement closure. 3. Gain final acceptance of the product 4. Complete financial closure 5. Hand off completed product 6. Solicit feedback form the customer about project 7. Complete final performance reporting 8. Index and archive records 9. Gather final lessons learned and update knowledge base ...
2 replies by Keith Novak and Yenny Peguero Jimenez
Jun 17, 2019 8:52 PM
Keith Novak
...
Interesting. I don't see that in Edition 6. What section did you find that in? I'm not challenging it whatsoever. I'm just wondering if there is more than in 4.7 Close Project or Phase, or they reorganized it.
Jun 18, 2019 8:27 AM
Yenny Peguero Jimenez
...
Hello, you can find it in the Rita Mulcahy's PMP Exam Prep Book Page 50, the Eighth edition, that is aligned with the PMBOK fifth edition.
Not directly related to your question, but just about the entire exam question bank focuses on what to do next.
Jun 17, 2019 6:37 PM
Replying to Yenny Peguero Jimenez
...
Hello Alvaro,
According to the PMBOK Fifth edition, here the order: 1. Confirm work is done to requirements 2. Complete procurement closure. 3. Gain final acceptance of the product 4. Complete financial closure 5. Hand off completed product 6. Solicit feedback form the customer about project 7. Complete final performance reporting 8. Index and archive records 9. Gather final lessons learned and update knowledge base ...
1 reply by Alvaro Couto
Jun 17, 2019 10:20 PM
Alvaro Couto
...
Keith,
We don't have an order in 6th edition - at least I could not find it. Jun 17, 2019 8:52 PM
Replying to Keith Novak
...
Interesting. I don't see that in Edition 6. What section did you find that in? I'm not challenging it whatsoever. I'm just wondering if there is more than in 4.7 Close Project or Phase, or they reorganized it.
We don't have an order in 6th edition - at least I could not find it.
It may come down to the quality of the mock exams you are taking. Try Rita's Fast Track and also PrepCast.
Rita is the best book to refer ...
Jun 17, 2019 6:37 PM
Replying to Yenny Peguero Jimenez
...
Hello Alvaro,
According to the PMBOK Fifth edition, here the order: 1. Confirm work is done to requirements 2. Complete procurement closure. 3. Gain final acceptance of the product 4. Complete financial closure 5. Hand off completed product 6. Solicit feedback form the customer about project 7. Complete final performance reporting 8. Index and archive records 9. Gather final lessons learned and update knowledge base
Hi, I've seen many posts on Rita's book. Is this PMP Exam Prep book is a text book like PMBOK, has only mock Exam questions or both? Also, does someone know the Rita's book edition referring to PMBOK 6th edition? Thank you so much !!!
...
1 reply by Stephanie Jaeger
Jun 18, 2019 10:35 AM
Stephanie Jaeger
...
9th edition of Rita's book is for PMBOK 6th edition
One point that I have not seen in the responses is to release the project team.
Jun 18, 2019 8:45 AM
Replying to Alvaro Couto
...
Hi, I've seen many posts on Rita's book. Is this PMP Exam Prep book is a text book like PMBOK, has only mock Exam questions or both? Also, does someone know the Rita's book edition referring to PMBOK 6th edition? Thank you so much !!!
|