Could anyone help me list down some examples of the deliverable in a construction ?
Please help me list down some good examples of deliverables in construction of Highrise Building Project?
Sort By:
Page: 1 2 next>
1. The building itself at a sufficient level of quality to meet requirements for all key stakeholders

2. Requirements, design & verification/validation documents

3. Multiple architectural blueprints

4. Approved permits

And the list goes on - Rami, I'm sure you could provide a few hundred or so :-)

Kiron
...
1 reply by SYED NASIR AHMED
Apr 11, 2020 2:42 AM
SYED NASIR AHMED
...
Thank for your valuable comment.
One more to possibly add (zoning dependent) is an impact assessment on local infrastructure and area businesses. Can roads/public transit support the increase of people coming and is there a positive or negative impact to other local businesses.
Jason
...
2 replies by SYED NASIR AHMED
Apr 11, 2020 2:42 AM
SYED NASIR AHMED
...
Thank for your valuable comment.
Apr 11, 2020 2:44 AM
SYED NASIR AHMED
...
Thank for your valuable comment.
Kiron, true that, thank you :-)

Syed

Here are some high level deliverables in sequence but it's not necessary that they all apply to your project:

Pre-Construction

1) Conceptual Design
2) Preliminary ROM Budget
3) Rezoning and Development Variance Applications
4) Working Drawings
5) BP Drawings + Submission
6) Class D Budget
7) Tender Drawings
8) Subcontractors Tenders
9) Building Permit
10) IFC Drawings

Construction

1) Ground Breaking
2) Sub-Structure Completion
3) Super Structure Completion
4) Substantial Completion
5) Final Occupancy

Be mindful that there are interim milestones in between those too. Hope this helps.

RK
...
1 reply by SYED NASIR AHMED
Apr 11, 2020 2:32 AM
SYED NASIR AHMED
...
Many thanks.
Apr 11, 2020 1:06 AM
Replying to Rami Kaibni
...
Kiron, true that, thank you :-)

Syed

Here are some high level deliverables in sequence but it's not necessary that they all apply to your project:

Pre-Construction

1) Conceptual Design
2) Preliminary ROM Budget
3) Rezoning and Development Variance Applications
4) Working Drawings
5) BP Drawings + Submission
6) Class D Budget
7) Tender Drawings
8) Subcontractors Tenders
9) Building Permit
10) IFC Drawings

Construction

1) Ground Breaking
2) Sub-Structure Completion
3) Super Structure Completion
4) Substantial Completion
5) Final Occupancy

Be mindful that there are interim milestones in between those too. Hope this helps.

RK
Many thanks.
Apr 10, 2020 4:57 PM
Replying to Kiron Bondale
...
1. The building itself at a sufficient level of quality to meet requirements for all key stakeholders

2. Requirements, design & verification/validation documents

3. Multiple architectural blueprints

4. Approved permits

And the list goes on - Rami, I'm sure you could provide a few hundred or so :-)

Kiron
Thank for your valuable comment.
Apr 10, 2020 6:23 PM
Replying to Jason Orloske
...
One more to possibly add (zoning dependent) is an impact assessment on local infrastructure and area businesses. Can roads/public transit support the increase of people coming and is there a positive or negative impact to other local businesses.
Jason
Thank for your valuable comment.
Apr 10, 2020 6:23 PM
Replying to Jason Orloske
...
One more to possibly add (zoning dependent) is an impact assessment on local infrastructure and area businesses. Can roads/public transit support the increase of people coming and is there a positive or negative impact to other local businesses.
Jason
Thank for your valuable comment.
Syed,

Rami has a great list.

There is a 2016 construction extension to the PMBoK Guide available from PMI bookstore.
While it does not have a separate list of deliverables, it provides additional knowledge about what to consider in construction projects.
...
1 reply by SYED NASIR AHMED
Apr 11, 2020 5:38 AM
SYED NASIR AHMED
...
Thank you for info.
Apr 11, 2020 5:31 AM
Replying to Thomas Walenta
...
Syed,

Rami has a great list.

There is a 2016 construction extension to the PMBoK Guide available from PMI bookstore.
While it does not have a separate list of deliverables, it provides additional knowledge about what to consider in construction projects.
Thank you for info.
Comments above are very valuable. I will write about my personal experience only, no more than that. I believe it has no sence to list here a list of deliverables, Why? Becasue this type of initiatives fully depends on the country where you will execute the initiative. For example, depending on the country you will work, goverment/local regulations plus union "regularions" must be fullfiled and those can be provided by you thanks you engage the right subject matter experts. That is a must I will write about what I did when i was assigned to my first project related to this without previous experience in 1998 in a hugh critical project in my country, Argentina. After that I was assigned to this type of project in other country and I followed the same basically. 1-perform elicitation searching into the internet about the matter. You will find a lot mainly because the goverments around the world publish it. 2-understand the domain by searching about PESTLE analisys and Porter Five Forces anaisys. Perhaps you will not find documents exactly indicatiing it is a PESTLE or Five Forces analysis but with that on account you will find the data. 3-Critical: identify the stakeholders mainly the subject matter experts. Each organization/company has its own way to perform this projects mainly if you work for the goverment or privite firms (i was in both projects).
Page: 1 2 next>  