Stuck with an Issues in MS Office , Help needed
Network:1175



I would like to know who to do the following tasks on MS project for a project involving 100 sites, which will be executed in parallel. How to add all the projects under one Master Project and track overall and individual progress, and do the following
tasks
Material tracking and reconciliation
Milestone based payments and baseline setting in MS project
Sort By:
Network:615



I would start here:

https://support.office.com/en-us/article/P...33-82d8392d119b
Network:185



I believe you could do this using MS Project Server, except for the material tracking and reconciliation which as is not within it's feature set as far as I recollect. It is a while since I used it though. You can use MSP to record material resources - see this link for how- but not to track their location.

https://ntrajkovski.com/2011/07/14/materia...s-project-2010/

I suspect there must be systems that are more suitable for your needs, perhaps others can advise...