What is different between Sprint backlog and Product backlog?
Network:55



What is different between Sprint Backlog and Product Backlog?
Sort By:
Network:17



Product backlog is a list of stories that are explained in details, whereas sprint backlog is a small set from Product backlog.

In other words, the BAs (or) Product Owners continue to pile the backlog items for the product as the feature concept unfurl to the need of the business. And from these backlog items, for a certain period of time, few items were considered as deliverable items for that sprint
...
1 reply by Tam Nguyen
Jun 29, 2017 10:48 PM
Tam Nguyen
...
thank you very much.
Network:162



A product backlog is the prioritized list of all stories for a given product, whether they're new features, bugs, or operational support. It is the sole repository for product requirements.

A sprint backlog is a set of the product backlog items that will be accomplished during a defined sprint. It also includes a plan to meet the sprint goal.
...
1 reply by Tam Nguyen
Jun 29, 2017 10:48 PM
Tam Nguyen
...
so many thank. I love your answer
Network:55



Jun 27, 2017 7:21 AM
Replying to Wade Harshman
...
A product backlog is the prioritized list of all stories for a given product, whether they're new features, bugs, or operational support. It is the sole repository for product requirements.

A sprint backlog is a set of the product backlog items that will be accomplished during a defined sprint. It also includes a plan to meet the sprint goal.
so many thank. I love your answer
Network:55



Jun 27, 2017 5:56 AM
Replying to DSK Chakravarthy
...
Product backlog is a list of stories that are explained in details, whereas sprint backlog is a small set from Product backlog.

In other words, the BAs (or) Product Owners continue to pile the backlog items for the product as the feature concept unfurl to the need of the business. And from these backlog items, for a certain period of time, few items were considered as deliverable items for that sprint
thank you very much.