Sprint Velocity
Network:265



If a sprint is cancelled in-between does it affect the team's average sprint velocity?
Sort By:
Network:2034



It should not. Velocity is a measure of what a team is able to complete within a given Sprint (completed).Canceling a sprint is not a common occurrence and is done if it is determined the sprint goal is no longer valid.
Network:104858



Fully agree with Andrew.

Even if half an activity was finished and the sprint was over, you only count the activities that were fully complete to count the team velocity.
Network:1160



Muthu -

I fully support Andrew & Rami's feedback - the one caveat I would offer is that velocity is a means to an end and not the end unto itself.

Like any other human-driven metrics, variation in velocity is to be expected and our focus needs to be on value, quality & stakeholder satisfaction.

Kiron
Network:265



Thanks Andrew, Rami & Kiron