Project Management Central

Please login or join to subscribe to this thread

Topics: PM in Academia, Schedule Management, Scheduling
Critical path using Start to start
Network:730



Are there any scenarios we need to calculate critical path for Start to start types
Of activities. Please share.
Sort By:
Network:801



With an SS dependency, unless there is a significant lead or lag, generally only one of the two activities would be on your critical path...

Remember that CP relates to the overall network diagram for the project and not just to a pair of tasks.

Kiron
Network:0



0. Start to start is a type of relationship/restraint/dependency, not a type of activity.

1. There are many scenarios where SS relationships are useful to model workflow in summary, where the detail necessary to use FS relationships is not justified. Then SS+lag is applied where the lag represents a certain volume of predecessor work that must be done before the successor can start. The lag may be only a millisecond, but the precedence exists nonetheless.

1a. A negative lag (i.e. a "lead") with a SS relationship seems almost exclusively for date-manipulation. I would question the underlying logic basis.

2. Whether one or both activities are on the Critical Path depends on upstream (predecessor) and downstream (successor) logic for both activities. There is nothing special about the SS relationship in the CPM/PDM calculations.

3. If a) the SS relationship actually drives the successor and b) the successor's downstream logic places it on the critical path, then most modern CPM software will also assign the predecessor to the critical path. The whole bar is colored red, though in fact only the start should be considered "critical."

Please login or join to reply

Content ID:
ADVERTISEMENTS

"It's a small world, but I wouldn't want to paint it."

- Steven Wright

ADVERTISEMENT

Sponsors