Montreal Shriners Hospital, Shriners Hos (9 Jan 12 - 30 Aug 15)
The Shriners hospital will have eight stories, and be linked to the new Montreal Children’s Hospital located at the McGill University Health Centre’s Glen site, allowing the two facilities to share ...
Technologies:
Industry: Construction/Architecture/Engineering
Role: Team Lead
Team:30


Restigouche Hospital (1 Jan 12 - 31 Dec 14)
Hospital
Technologies:
Industry: Construction/Architecture/Engineering
Role: Team Lead
Team:20


Sainte-Justine University Hospital Centr (1 Mar 11 - 30 Sep 14)
The Sainte-Justine UHC modernization project consists in expanding the existing facility by constructing a building for specialized units (SUB) as well as a new research centre. 450 M$ / 127,840 sq...
Technologies: Oracle Primavera Risk Analysis @Risk
Industry: Construction/Architecture/Engineering
Role: Team Lead
Team:100


MUHC Glen Campus, McGill University Heal (1 Jan 09 - 30 Sep 14)
The MUHC is a hospital complex that will bring together the Royal Victoria Hospital, the Montreal Children’s Hospital, the Montreal Chest Institute, the Cancer Centre and the MUHC Research Institute....
Technologies: Oracle Primavera Risk Analysis @Risk
Industry: Construction/Architecture/Engineering
Role: Team Lead
Team:400


Adresse Symphonique (1 Jan 08 - 30 Nov 12)
Fast-track design-build of a 2,100-seat concert hall. The auditorium is equipped with sophisticated stage systems for the performance of acoustical or amplified concerts. Build to be M1 in external ...
Technologies:
Industry: Construction/Architecture/Engineering
Role: Team Lead
Team:30