Then Nobody’s An Expert

linkedin twitter facebook Request to reuse this  

There’s a story I’ve used as an example in this blog before, about a display at the New York Metropolitan Museum of Art that was trash. I’m not engaging in hyperbolic art criticism here – it was literally litter, framed. One prescient critic pointed out that, if everything is “art,” then nothing really is, and I wholeheartedly agree with that assessment.

Meanwhile, back in the PM Universe, I’ve noticed another troublesome trend, particularly among Earned Value practitioners. It seems that almost every EV practitioner I’ve come across thinks of themselves as an “expert,” and can be counted on to allude to it, either in their CV or in discussions about how project management information systems ought to function or be implemented. Sometimes their claims to a high level of expertise have some viability, but other times they’re pretty spotty.

As An Example…

I’ve also already conveyed the story of the young woman who pretentiously demanded that all the managers in the room defer to her “expertise” in EV because she had the PMP® certification. I’m not even sure if she was aware that a significant percentage of the people she was trying to one-up also had PMP®s, or if she cared. She was an expert, by gum, and everyone else was to acknowledge her superiority by either agreeing with her, or else shutting up. It’s unfortunate she chose to use her new PMP® as a bludgeon rather than an accomplishment milestone, but that’s what she did. The funny thing about that story was that she had just asserted a concern that, on that particular project’s Cost Performance Report (Format I), the Earned Value figure didn’t equal the cumulative actual costs (ACWP).

“That’s right” the contractor’s project controls analyst calmly replied, “because that’s not how you calculate Earned Value.”

“Do you know PMI®?!” she stormed. “I’m a PMP®!”

The ensuing percentage of meeting participants who either rolled their eyes or face-palmed probably broke some sort of record.

Unfortunately, It’s Not That Rare

But I know for a fact that this phenomenon is not confined to the naïve-but-arrogant set. In several supposedly high-level meetings of people who have presented themselves as highly advanced in the field of cost performance management, many known-invalid arguments have cropped up, as if they should carry the day and settle the argument then taking place. I tease accountants a fair amount in this blog, but I will say this for them: they generally don’t allow arguments like the sunk-cost fallacy to enter into management decisions, much less let them completely settle a matter.

Conversely, it seems that EV “experts” can be bamboozled by even the simplest syllogisms, as if none of them had ever read Aristotle. Get a room full of these guys into an animated conversation, and the question-begging becomes commonplace. For the record, the phrase “this begs the question…” is not analogous to “this raises the question…”  The syllogism Begging the Question means to assume as true a premise that is either not established as fact, or else has not been agreed to by all participants. In the example I’m thinking of (and, again, have mentioned in a previous blog), the self-proclaimed expert was demanding deference because he had travelled overseas to consult on the topic of Earned Value. I swear I am not making this up. In fact, the fellow became rather irate when I called him on his clearly invalid assertion, that having one’s passport stamped somehow imparts advanced cost performance knowledge. Alarmingly, I had the distinct impression that, had I not done so, no one else in the room would have.

Why This Is A Problem

“So, Michael, what’s the problem here, really?” I can hear some readers say. “What if these EV practitioners think a lot of themselves? Whom does that hurt? Isn’t confidence a good thing, particularly in a consultant?” Well, yes and no. When these consultants start, say, writing guidance documents that are chock-full of these utterly unsupported hypotheses, and those guidance documents get adapted by auditing agencies, then the entire field of Earned Value Management suffers.

Then there’s the problem I began describing in the first paragraph. If everyone is an expert, then it has the same effect as grade inflation at the Ivy League schools. So what if you graduated with honors from Harvard? So did 91% of your fellow class mates![i]

There’s really no point in trying to correct this problem through encouraging all these EVM experts to behave better. That’s simply not going to happen. I mean, look at the offerings from the typical EV symposium. I can almost guarantee that a majority (91%, even) will fall into one of the following categories:

  • I saved my project by embracing EV (or its subvariant, My Project Did Great, And We Used Earned Value),
  • Everyone should be doing EV, or
  • The basics of EV, for the bazillionth time.

…and that’s it. Only occasionally do you see any new research proffered, or even an exhaustive analysis of past projects that have performed well using basic techniques compared to failed ones that did not. And just to be clear, if the EV seminars and symposiums are dropping the ball on advancing legitimate management science theories, then the venues that do perform this function are left to people like ProjectManagement.com bloggers.

As I’ve maintained in previous posts, the answer here is to return to the basics of true management science analysis. For those who have read Aristotle, we should embrace those writers who rely on logos, and eschew those who rely on ethos, i.e., the “experts.”

But, since everyone’s an expert, then nobody really is, so this problem is kind of solving itself.

 


[i] Retrieved from http://www.sfgate.com/news/article/Harvard-s-dirty-little-secret-is-out-grade-2868775.php on August 5, 2017, 2100 MDT.

Posted on: August 07, 2017 10:26 PM | Permalink | Comments (3)

Perry Mason’s Initials Are “PM”

linkedin twitter facebook Request to reuse this  

My oldest son graduated Magna Cum Laude from a fairly prestigious law school, and works as a prosecutor. On those occasions when he visits home and gets into conversations with me, I sometimes like to tweak him by deliberately mis-using legal terms when I want to take exception to an assertion he’s made. A recent example went like this:

“Objection, your honor! Facts not entered as evidence!”

“You realize” he replied, “that what you just said is almost literally gibberish.”

“Not according to the television law shows I’ve seen.”

“Then you need to watch a higher caliber of law show.”

Later, when talking about that exchange with my wife, I admitted that I should stop doing that, lest I increase the odds of my son skipping trips back home in order to avoid such face-palm moments. But I hastened to add that, if there were television shows about Project Management (similar to “Law & Order,” would ours be “Cost & Schedule?”), and some of the terms we use on a regular basis were to seep into the common lexicon, I would be more tolerant of their modified, hipster connotations than our legal professional counterparts.

And then, almost as those words were leaving my mouth, I realized that they were utterly false.

In fact, it drives my face directly into my palm when I hear project managers misuse terms with which they should be completely familiar. It’s particularly cringe-worthy when the speaker has some sort of PM certification. A quick list includes the following. NOTE: all of these are actual quotes that I have heard in my time in PM.

“This task is too important to not be on the critical path.”  While not almost literally gibberish, it is extremely goofy, as any entry-level scheduler can tell you. Whether or not a task in a schedule network appears on the critical path has nothing whatsoever to do with its profile, or perceived “importance.” Its presence on the critical path is solely determined by its duration and schedule logic (e.g., which tasks have to be completed before others can begin). Now, I will concede that, once a CPM-capable software package has performed the forward and backward passes on the schedule network, and has identified the critical path, your typical PM will place more importance on the performance of the activities that are on it. But to assume that high-profile or perceived-to-be important tasks must therefore be on the critical path is a sure sign that the person who is asserting so has no idea what they’re talking about.

“There’s an 80% confidence interval that this project will not exceed (N) dollars.” Yeah, and there’s a 100% confidence interval that the person or persons who have performed the “analysis” that supports such an absurd position have absolutely no way of knowing that for certain. How do risk managers and analysts come up with the 80% confidence interval figure? Typically, it’s based on the following data points:

  • Original estimate, in both cost and duration (at the level of the Work Breakdown Structure where the analysis occurs),
  • Estimates of the odds of the task experiencing unplanned events,
  • Estimates of the impact that such events may have,
  • A calculation of the odds of occurrence, multiplied by the estimated impact, and then subtracted from the original budget in order to isolate the cost or schedule contingency amount.
  • If a Monte Carlo analysis in used, the risk analysts will also pre-select a type of leaning-bell curve with which the artificially-generated “events” should conform. (Did I mention that the result, represented graphically, of the artificially- [or “randomly- “] generated events, is pre-selected?)

Okay, so what’s wrong with all this? Consider the steps, in order:

  • Subjective data.
  • Highly subjective data.
  • Obscenely subjective data (can we even really call it “data”?)
  • Statistical analysis of obscenely subjective data.
  • Further analysis of obscenely subjective data, where the results are already established.

Need I say more?

“We’ve spent more than we budgeted for the month, so we have a negative cost variance.”

I can’t even.

So, if you hear these phrases spoken aloud, and it’s not a case of a father exercising his right to irk his children, you will know that the speaker is not an authentic project manager.

Or else he just needs to watch a higher caliber of PM shows.

 

Posted on: July 31, 2017 10:24 PM | Permalink | Comments (7)

Yes, Absolutely, Burn Henrietta

linkedin twitter facebook Request to reuse this  

There’s a classic scene in the 1956 movie, Around the World in 80 Days, where English aristocrat Phileas Fogg (played perfectly by David Niven) is on the last leg of his epic journey, and finds himself in the mid-Atlantic on board the tramp steamer Henrietta. Due to storms and adverse winds, the Henrietta runs out of fuel well short of England, and, if Fogg can’t make it back to the starting spot of his journey on-time, he will lose his wager, and can expect a future of poverty. Realizing his situation, he makes a bold decision: he purchases the steamer on the spot, and then orders all flammable materials on-board that do not directly contribute to the ship’s navigation capabilities to be broken up and fed to the furnaces that drive the steam system.

As various wood planks and assorted burnable pieces of the Henrietta arrive in the ship’s engine room, the ship’s first officer, played by Andy Devine, laments their loss. But, when the wooden carved figure from the bowsprit arrives, the first officer cries aloud “No, not Henrietta!” (presumably, the nickname of the bowsprit itself.)

Alas, Henrietta the Figurehead herself is fed to the furnaces, and the ship makes it to port soon enough for Fogg to complete his journey on-time, and collect on his bet.

What does this have to do with Project Management? Well, I’m glad you asked.

There have been multiple efforts of late, both in private and public sector PM circles, to develop something called “Earned Value light,” or an Earned Value Management System that is not overly encumbered by superfluous techniques or processes, and delivers cost and schedule performance information with minimal cost and fuss. I think the existence of such initiatives is ipso facto evidence that those I have previously referred to as “processors” have gained ascendency in the project management world, and have made something as basic and straight-forward as a working EVMS into an extremely difficult endeavor. It may be too late to turn back their insidious encroachments into legitimate management science, but I mean to make the attempt by asking: what, exactly, is an EVMS for? What’s its purpose? And, if that question can be clearly and cleanly answered, the next one is: which current practices attached to the set-up and maintenance of Earned Value Systems are superfluous, and should be dissuaded, if not out-and-out abandoned?

Here's my take: Earned Value Management Systems exist for one purpose, and one purpose only: to put into the hands of the project’s decision-makers the cost and schedule performance information they need to make, well, informed decisions.

That’s it.

Michael, Do You Realize What You’re Implying?

Yes, I’m crystal clear on what that definition implies for the answer to the follow-on question. For, if my definition is right, it follows that these practices have nothing at all to do with Earned Value:

  1. The creation of a time-phased Estimate to Complete,
  2. Comparing actual costs at the line-item level to their counterparts in the cost baseline’s Basis of Estimate (BoE),
  3. Performing a “bottoms-up” Estimate at Completion,
  4. Mandating that an extremely accurate and recent Master Resource Dictionary be used in time-phasing the budget,
  5. …among many other practices and techniques that have been larded onto essential EVM, with the blessings (if not insistence) of so-called “experts.”

However, some prominent procedure or guidance-generating organizations have pushed these add-ons relentlessly, asserting outright that to avoid them is to fail to “do” EV correctly, which I hold to be so much rubbish.

It essentially boils down to this: put yourself in Phileas Fogg’s shoes, except in this case, rather than come up with the criterion needed to get the S.S. Henrietta to her destination (reminder: burnable with no connection to the ship’s ability to navigate), you need to come up with the criterion for producing usable cost/schedule performance information with an absolute minimum of effort, time, and cost. Which “must-have” aspects of EV would you abandon? Which would you keep? From my point of view, get rid of anything – anything – that did not directly support the collection of a basic time-phased budget, actual costs at the reporting level of the Work Breakdown Structure, and a reliable estimate of the tasks’ percent complete at the end of the reporting period, again at the reporting level of the WBS. For example, from the list above,

  1. …serves to help improve resource allocation (theoretically – I’m not convinced, but that’s what its adherents claim),
  2. …is supposed to improve the quality of the original estimates,
  3. …comes from sheer ignorance of the accuracy of calculated EACs and the inaccuracy of re-estimated ones, and
  4. …is also supposed to improve the quality of original estimates.

None of which, obviously, have anything to do with delivering cost and schedule performance information to PMs and other decision-makers. Everything else – everything – is superfluous, and should be abandoned.

Even Henrietta.

 

Posted on: July 24, 2017 10:12 PM | Permalink | Comments (7)

Hey! Who Put This Venn Diagram In My Pudding?

linkedin twitter facebook Request to reuse this  

Next to the overuse of the word “like,” the most irksome trend in modern English usage has to be, in my opinion, the phrase “the proof is in the pudding.” It may be a case of confirmation bias on my part, but this idiotic phrase appears to be everywhere. The original version, which dates back at least to 1605, has the virtue of actually making sense: the proof of the pudding is in the eating, meaning that the cooks can argue about the proper way of making a pudding all they want – the true test will come when the dish is actually consumed.

So, how did the highly irksome version of this saying come into existence? I could find no authoritative analysis, though the consensus appears to be that the original was shortened to “the proof of the pudding,” which was then mis-heard or mis-applied into its grating iteration. I mean, seriously, would those who use this phrase simply stop and think about it for just a moment? When I took a college-level course in logic, the only “proofs” the professor was interested in was the depiction of the premises and conclusions of an argument in a Venn Diagram. Okay, so if the “proof is in the pudding,” did somebody put a Venn Diagram into the pudding prior to its being set? And, if so, wouldn’t it be hard to read afterwards? In my book, the use of the idiotic version of this phrase automatically renders whatever the writer has to say highly suspect, if not entirely worthless.

Virtue Signaling? No, this is Stupid-Signaling

Think I’m ranting (again)? Consider the real-life example I’ll pull from when I was instructing new, usually young Project Controllers in the art and science of cost and schedule performance systems. Just prior to the module on preparing the Variance Analysis Report (VAR), I would stop the presentation and walk over to the classroom’s white board, and write the word “his.” I would then call on one of the students, and ask them to read what I had written. After receiving the answer, I would ask, “Is this misspelled?”

“No.”

I would then write the word “hers,” and call on another student with the same two questions. I would continue in this vein with “ours” and “theirs,” each time receiving the same answer to the question “Is this misspelled?”

I would then write “Its,” and the classroom would usually laugh a little, realizing where I was going with this.

“You laugh,” I would respond, “but I will guarantee that, if I were to perform a quality check on everybody’s VARs one year from now, I will find at least one instance of ‘it’s’ being used instead of the real impersonal possessive pronoun. For the record, ‘it’s’ is a contraction of ‘it is,’ which is something most people are supposed to learn by fifth grade, at the latest. It may seem trivial, but I will also guarantee that, if your customer sees this error in your VARs, they won’t be impressed with your analytical or reporting ability. In fact, they’re likely to think whatever you have written to be highly suspect, so, please don’t make this error.”

Back in the Project Management world…

…we have to deal with quite a few very basic errors in assumptions about management science that are similarly entrenched in the common business consciousness, but just as infuriatingly wrong, and irksomely so. Take the very basic definition of the term “cost variance.” According to many websites (I’ll pick on Study.com[i]), a cost variance is “the differences between the planned budget and what was actually spent.”

Ummm, no, it’s not (see how easy it is to use to “it’s” correctly?).

A Cost Variance, as any certified PM readily knows, is the difference between the Earned Value and the Actual Costs. A Schedule Variance is the difference between the Earned Value and the budget, or “planned budget.” In reality, comparing the budget to the actuals, as commonplace an “analysis” as that is, is virtually worthless. Consider the following payoff grid:

 

 

Real Negative Cost Variance

Real Positive Cost Variance

Positive Spend Variance

You’re doing poorly, but think you’re doing great (does it get any more dangerous from a management point of view?)

Coincidentally Accurate

Negative Spend Variance

Coincidentally accurate

You’re doing great, but think you’re doing poorly

 

In half of the possible outcomes, comparing budgets to actual costs returns the right answer, but only coincidentally so. However, in the other half of the instances where such a comparison returns bad information, one of those outcomes would lead you to a false sense of security, or project well-being, when the opposite perception is called for. And even if you don’t become lax with your decision-making, real problems are going unaddressed, which usually leads to them becoming large (or even fatal) ones. You’re almost literally better off flipping a coin, and making decisions based on that outcome.

And that, perhaps, is the greatest benefit of a certification. It transmits to potential employers and customers that its holder knows the valid versions of common management analysis techniques, and will eschew the more popular, but irksome versions.

And knows how to spell the impersonal possessive pronoun.

And never says “the proof is in …”, well, you know.

 


[i] Retrieved from http://study.com/academy/lesson/cost-variance-definition-formula-analysis.html on 16 July 2017, at 11:29 MDT.

Posted on: July 17, 2017 10:31 PM | Permalink | Comments (2)

The Electric Kool-Aid Certification Test

linkedin twitter facebook Request to reuse this  

I’ve worked with an organization that had the habit of acting like the next manager being brought in was some kind of Tom Wolfe-esque microeconomic rock star, whose name should have been instantly recognizable to the hoi polloi. After building up this person relentlessly, this person would finally arrive to take up their new position, and…

Well, nothing.

Nothing spectacular, no new ways of approaching the problems the project team faced, no novel implementation strategies to known workable tactics, nothing. They wouldn’t even bother figuring out how the current systems operated. Oh, they would crank up the energy level for a time, and get into meetings where they would strongly emphasize trite and clichéd axioms. But as far as actually advancing a capability, they were able to deliver only a whole bunch of nothing.

Not. A. Thing.

And Then, After Fleeing to Mexico…

Eventually these “superstar” managers would be re-assigned, and another one breathlessly announced, and the cycle would begin again.

After witnessing this cycle repeat a few times, I began to notice something that all these new managers had in common: none of them were certified.

A few weeks back I blogged about the difficulties inherent in working for organizations where loyalty, not talent, was considered the key attribute for the staff to demonstrate. The pathologies inherent in such an organizational approach are legion, but one of the key indicators that an organization is so situated is that they do not place a premium on professional certifications. In those cases where an apathy is associated with the attainment or holding of a relevant professional certification, and it is combined with a laxness about educational requirements, then the odds that the organization is even remotely based on a meritocracy are low, indeed.

Which kind of puts the whole certification impetus upside-down. I mean, when I was pursuing my certs, it was in an effort to signal to current and future employers that my level of expertise was more advanced than my non-certified competitors and colleagues. And almost exclusively that’s how the attaining-your-certification industry advertises its worth, by promising to make the successful cert candidate, well, more successful in the long run. But what I have observed is that it’s the winning organizations that will attract certified project managers, project controllers, and cost estimators in a way that their more poorly-functioning competitors do not.

Who’s being tested here, anyway?

To be precise, I am not saying that those organizations that make it a point to send their employees to certification training and reimburse them for their certifications are going to automatically begin to out-perform their competitors. What I am saying is that a fairly reliable sign that an organization is at least somewhat merit-based in its hiring and promotion practices will tend to attract more highly educated and certified employees, and that those dysfunctional organizations, where loyalty is the coin of the advancement realm, well, won’t. Indeed, one of the best ways to prevent a given hiring manager from filling a key position (or any position, really) with an underqualified – or even inept – candidate, who just happens to be an old friend, is to strictly enforce standards for even being interviewed for the position. In the project management world, educational requirements (past the attainment of a Bachelor’s or Master’s Degree) can be tricky – they don’t call PM “the accidental profession” for nothin’. Successful PMs come from extremely varied areas, including computer science, engineering, the hard sciences, or even business, among others. But a PMI® certification – that’s something different. That communicates that, regardless of background, its holder knows a thing or two about managing projects. Because of this, an unintended consequence of including it as a prerequisite is that it can function as a brake on cronyism, at least in its most blatant manifestations.

So, all this time, when you saw a requirement for a PMP® just to apply for a project management job, you thought they were testing you. In reality, the whole time they were advertising their own suitability as an organization worthy of your talents.

Posted on: July 10, 2017 10:57 PM | Permalink | Comments (4)