Task                                              050                                                - Design Cross-System Interface Changes050 Design Cross-System Interface Changes Task                                              070                                                - Review Change Specifications070 Review Change Specifications

Task 060 - Identify Operations Areas

Role Apportionment Weights
Inputs
Outputs
Roles
Templates for this Process
Templates for this Stage
Index
ADVERTISEMENT
linkedin twitter facebook Request to reuse this  

Description

Identify the specific areas within Operations to take responsibility for implementing the following changes included in the design specifications:- file or program changes that affect JCL- table changes- system-related or teleprocessor component changes - views changes- new or changed database files...

Please login/register as a Premium Plus member to continue reading. You must be a Premium Plus member to access this content.


Role Apportionment Weights


Inputs


Outputs


Roles


Predecessors

MNT.MAD.0400.010 Task - Design Data Changes - Dependency: Finish - Start
MNT.MAD.0400.020 Task - Design Screen Changes - Dependency: Finish - Start
MNT.MAD.0400.030 Task - Design Document Changes - Dependency: Finish - Start
MNT.MAD.0400.040 Task - Design Program & Module Changes - Dependency: Finish - Start
MNT.MAD.0400.050 Task - Design Cross-System Interface Changes - Dependency: Finish - Start