What is your preferred way to calculate contingency?

linkedin twitter facebook   Estimating   Risk Management  
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Do you use EMV, expert judgement or just add a percentage as a buffer to calculate your contingency.
Sort By:
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
EMV based on identified risks but sanity check the aggregated amount via expert judgment.

Kiron
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
I normally add percentages per item based on previous experience. Other time I use EMV.
avatar
Kevin Drake Perth, Western Australia, Australia
I think it is a combination of SME, EMV, Risk and percentage.
avatar
Oliver Schneidemann Transformation Professional New York, NY, United States
+1 on estimating value at risk of high-probability risks, and use that amount. Senior leaders who question project budgets' contingency will find it hard to argue with that.
avatar
Riyadh Salih Saskatchewan, Canada
I use percentage, EMV, & predetermined guideline from AACE International
(Association of Advancement for Cost Engineering)
avatar
Anish Abraham Privacy Program Manager| University of Washington Auburn, Wa, United States
I normally use expert judgement and take a percentage of the cost of the project to calculate the contingency amount.
avatar
Ruth Marina Lopez Perez Responsable TI| INSTITUTO DE PREVISION SOCIAL MILITAR - NICARAGUA Masaya, Los Madrigales, NindirĂ­, Nicaragua
I use EMV and expert judgement.
avatar
Sylvain Costy CIO| Handball French Federation Draveil, France, France
On my side, it's an aggregate of previous experience, expert jugement and risk estimating. It depends of the project.
avatar
Quinton van Eeden Enabling Quality Decisions by Addressing Uncertainty| TPG GRC Johannesburg, Gauteng, South Africa
Integrated Cost Schedule Risk Analysis as per AACE Recommended Practices and risk tolerance of project owner

Please login or join to reply