You are utilizing a technique of reconciling the expenditure of funds with the funding limits set for the project. As per the variance between expenditure of funds and planned limit, you are trying to reschedule activities to level out the rates of expenditures. This technique is known as:
A. Funding limit reconciliation
B. Cost aggregation
C. Reserve analysis
D. Forecasting Saving Changes...