A project is in the final stages of testing when it receives a major change request from the customer which would delay the final delivery of the project by 2 weeks. What should the Project Manager d

linkedin twitter facebook   Integration Management  
avatar
Moloy Chakraborty Principal Project Manager| WSP UK LTD High Wycombe, Buckinghamshire, United Kingdom
A project is in the final stages of testing when it receives a major change request from the customer which would delay the final delivery of the project by 2 weeks. What should the Project Manager do NEXT?

a) Create a change request and go through the change management process
b) Evaluate the impact of the change
c) Communicate the implication of the change to the customer
d) Adjust the project management plan and baseline
Sort By:
< 1 2 >
avatar
Tamer Zeyad Sadiq Assistant Cost Manager| Turner & Townsend Riyadh, Ar Riyad, Saudi Arabia
This is as PMP exam really!!!. We should follow change request procedures step by step exactly!!! I learned from Rita and PMSTUDY!!! There a lot questions about change request in PMP exam!!!

As Rami said exactly, these steps we should follow one by one!!!
avatar
Tamer Zeyad Sadiq Assistant Cost Manager| Turner & Townsend Riyadh, Ar Riyad, Saudi Arabia
This is as PMP exam really!!!. We should follow change request procedures step by step exactly!!! I learned from Rita and PMSTUDY!!! There a lot questions about change request in PMP exam!!!

As Rami said exactly, these steps we should follow one by one!!!
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
May 11, 2018 8:06 AM
Replying to Kevin Drake
...
YOu are enjoy it Rami
Iam what Kevin ? :D
< 1 2 >