Which is the most important parameter against which project schedule should be measured to recommend corrective and preventive actions?

linkedin twitter facebook  
avatar
Moloy Chakraborty Principal Project Manager| WSP UK LTD High Wycombe, Buckinghamshire, United Kingdom
Which is the most important parameter against which project schedule should be measured to recommend corrective and preventive actions?

a) Schedule Baseline
b) Work Performance Measurement
c) Earned Value Technique
d) Variance Analysis
Sort By:
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
A - Schedule Baseline - Progress is always measured against it.
avatar
MANSOUR THABET ALQUBATY System Controller| Teleyemen Sana'A, N/A, Yemen
Hi,

Yes, A is the correct answer.
Agree with Rami as we always measure against baseline(s) (for cost, schedule, scope).

We used to say baseline terminology for either (scope,schedule, and cost).

BR,
Mansour
avatar
Sonali Malu Maharashtra, India
A - Schedule baseline