Estimate activity resource ?

linkedin twitter facebook   Estimating  
avatar
Dr.Shaban Osman |Consultant |Instructor |Author|| freelancer Elshourk, Egypt
Dear all, in pmbok 6 edition this process is shifted to resource management ,but i think that it preferred to be in schedule as in 5 edition ,it was more logic ?
Sort By:
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
As you know one of the biggest changes was to explicit change the scope of word "resource" to all type of resources. Because of that all related to it was concentrated into the resource management are. Take into account other big modification is inside the inputs definition where you can see the detail of some items like "Project documents". At the end, the idea (as far as I know) was to concentrate all related to one item into one specific area for each item.
...
1 reply by Dr.Shaban Osman
May 17, 2018 4:31 AM
Dr.Shaban Osman
...
Many ,thanks .
I mean that when we explain to out audience the project schedule ,we must explain resources and how it will be determined .
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Why do you feel it's more logical under Project Schedule Management than Project Resource Management? There is already Estimate Activity Durations which is related to time/schedule.
...
1 reply by Dr.Shaban Osman
May 17, 2018 4:32 AM
Dr.Shaban Osman
...
Ok,noted but how can we estimate activity duration without estimate activity resource .Duration is based on available resource .
avatar
Dr.Shaban Osman |Consultant |Instructor |Author|| freelancer Elshourk, Egypt
May 15, 2018 5:04 PM
Replying to Sergio Luis Conte
...
As you know one of the biggest changes was to explicit change the scope of word "resource" to all type of resources. Because of that all related to it was concentrated into the resource management are. Take into account other big modification is inside the inputs definition where you can see the detail of some items like "Project documents". At the end, the idea (as far as I know) was to concentrate all related to one item into one specific area for each item.
Many ,thanks .
I mean that when we explain to out audience the project schedule ,we must explain resources and how it will be determined .
...
1 reply by Sergio Luis Conte
May 17, 2018 4:50 AM
Sergio Luis Conte
...
Yes, you are right. All you need to do that is inside the inputs (6.4.1). See what is named "6.4.1.2. Project Documents". That is new in the PMBOK Guide. I do not like it too much but is a new way to list things you need as inputs and thngs you create/modify as output.
avatar
Dr.Shaban Osman |Consultant |Instructor |Author|| freelancer Elshourk, Egypt
May 15, 2018 9:33 PM
Replying to Sante Delle-Vergini, PhD
...
Why do you feel it's more logical under Project Schedule Management than Project Resource Management? There is already Estimate Activity Durations which is related to time/schedule.
Ok,noted but how can we estimate activity duration without estimate activity resource .Duration is based on available resource .
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
May 17, 2018 4:31 AM
Replying to Dr.Shaban Osman
...
Many ,thanks .
I mean that when we explain to out audience the project schedule ,we must explain resources and how it will be determined .
Yes, you are right. All you need to do that is inside the inputs (6.4.1). See what is named "6.4.1.2. Project Documents". That is new in the PMBOK Guide. I do not like it too much but is a new way to list things you need as inputs and thngs you create/modify as output.