Project closing ?

linkedin twitter facebook  
avatar
Dr.Shaban Osman |Consultant |Instructor |Author|| freelancer Elshourk, Egypt
From my experience in construction project ,i understand that close the project is mean final closing after passing the warranty and guarantee period .In our project we divide closing into two stage primary closing and final closing .
My question is ,why it is not clear in Pmbok this matter ?
Sort By:
avatar
Kevin Drake Perth, Western Australia, Australia
I agree with you, in Oil and Gas we have the same.
...
1 reply by Dr.Shaban Osman
May 18, 2018 8:14 AM
Dr.Shaban Osman
...
Sure , i think that its in all engineering projects .
avatar
Akhilesh Sooraj Team Leader - Process & Methods Team Leader| KNORR-BREMSE Technology Center India Private Limit Pune, Maharashtra, India
Totally depends on the project scope definition.

In a product development company, it could be 2 separate Projects.
1. Development Project and finishes the project once the handover to regular maintenance/operations department is done since the target of construction Project is accomplished by delivering the building on time is accomplished
2. Support /Operation project (s)- to support the issues arising in the lifetime of the building and warranty issues as and when it comes. this will end like you said- after guarantee period.

I am not an expert in the construction projects. So I could be wrong also
...
1 reply by Dr.Shaban Osman
May 18, 2018 8:18 AM
Dr.Shaban Osman
...
Thanks ,sir
avatar
Kevin Drake Perth, Western Australia, Australia
Closing snag list is an important part of the closing and it is the responsibility of the project manager and it is in PMBOK as part of responding to the inspection.

However, commissioning and warranty period could stretch to 5 years and usually, a commissioning manager will be appointed to manage that period usually.

Maintainance/ support is part of the operation.
...
1 reply by Dr.Shaban Osman
May 18, 2018 8:20 AM
Dr.Shaban Osman
...
I agree with you ,but i mean the period between primary closing and final closing it may not include warrant e period which reside to operation manger .
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Shaban -

Project lifecycles vary widely between industries and companies. The PMBOK provides a framework which can be used as a reference but is not expected to cover all possible permutations and combination of approaches.

I haven't read it, but I wonder if the Construction extension to the PMBOK Guide covers this specific nuance for closing?

Kiron
...
1 reply by Dr.Shaban Osman
May 18, 2018 8:16 AM
Dr.Shaban Osman
...
Ok, but its a fundamental topic in all project.We want Pmbok to be good guide with complete information .
avatar
Dr.Shaban Osman |Consultant |Instructor |Author|| freelancer Elshourk, Egypt
May 18, 2018 1:47 AM
Replying to Kevin Drake
...
I agree with you, in Oil and Gas we have the same.
Sure , i think that its in all engineering projects .
avatar
Dr.Shaban Osman |Consultant |Instructor |Author|| freelancer Elshourk, Egypt
May 18, 2018 7:53 AM
Replying to Kiron Bondale
...
Shaban -

Project lifecycles vary widely between industries and companies. The PMBOK provides a framework which can be used as a reference but is not expected to cover all possible permutations and combination of approaches.

I haven't read it, but I wonder if the Construction extension to the PMBOK Guide covers this specific nuance for closing?

Kiron
Ok, but its a fundamental topic in all project.We want Pmbok to be good guide with complete information .
avatar
Dr.Shaban Osman |Consultant |Instructor |Author|| freelancer Elshourk, Egypt
May 18, 2018 1:59 AM
Replying to Akhilesh Sooraj
...
Totally depends on the project scope definition.

In a product development company, it could be 2 separate Projects.
1. Development Project and finishes the project once the handover to regular maintenance/operations department is done since the target of construction Project is accomplished by delivering the building on time is accomplished
2. Support /Operation project (s)- to support the issues arising in the lifetime of the building and warranty issues as and when it comes. this will end like you said- after guarantee period.

I am not an expert in the construction projects. So I could be wrong also
Thanks ,sir
avatar
Dr.Shaban Osman |Consultant |Instructor |Author|| freelancer Elshourk, Egypt
May 18, 2018 2:08 AM
Replying to Kevin Drake
...
Closing snag list is an important part of the closing and it is the responsibility of the project manager and it is in PMBOK as part of responding to the inspection.

However, commissioning and warranty period could stretch to 5 years and usually, a commissioning manager will be appointed to manage that period usually.

Maintainance/ support is part of the operation.
I agree with you ,but i mean the period between primary closing and final closing it may not include warrant e period which reside to operation manger .