Question on current Project Status

linkedin twitter facebook  
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
A Project Team has a performance rate in which half of the assigned tasks are completed each day.

If at any given moment of the day the PM asks the project team for a status of the 600 tasks assigned, how many remaining tasks would they have after four days of work?
(the calculation is done from the moment in time the PM is checking the status report)

A) 300 tasks in the log
B) 150 tasks in the log
C) 37,5 days in the log
D) no tasks remaining in the log
E) none of the answers above
Sort By:
< 1 2 3 >
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
50% 50% 50% 50% 50% 50% 50%
5 6 7 8 9 10 11
6 5 4 3 2 1 0
18.75 9.38 4.69 2.34 1.17 1 0
< 1 2 3 >