I'm using MS Project 2003 Professional......while printing out the

linkedin twitter facebook  
avatar
Dale Beckett San Ramon, Ca, United States
MS Project 2003 Professional, "Who Does What" report & recurring tasks......while printing out the "Who Does What" report under “Assignments”, the “Duration” for all instances of the recurring task is posted in the "Work" column for recurring tasks. I would expect a summation of the Work required to complete all the instances within each recurring task not the overall duration it takes to complete all tasks.....is this a bug or does it just work this way? It totally skews the number of total work hours listed for each resource on this same report…..any comments, confirmation, suggestions on how to get the total work hours on the “Who Does What” report for each resource to be accurate when recurring tasks are listed would be appreciated.