An oil company is laying a 1,000 km pipeline to reduce cost of transportation of oil, which is currently carried by oil tankers via road. The pipeline will pass through 4 different countries, over diverse terrain and some sections will be under water as well. The work will be executed by the company’s staff and 4 contractors, each handling a separate section, and will take about 5 years. This is most likely an example of:
a)A large project with several sub-projects
b)A program
c)A portfolio
d)A sub-portfolio, part of a strategic change initiative Saving Changes...