When I generate a milestone report (Reports In-Progress Milestone Report) in MS Project 2016, I get a blank screen with no data. What should I do? Is there a specific way to enter the milestones for it to appear on the report?
Please help. Saving Changes...
Sort By:
Kyriakos ChristofiPhD student| European University CyprusLimassol, Limassol, Cyprus
Hello, I think if you put 0days in the duration will be fine. Alternatively you can check in the project plans templates.! Saving Changes...
RAJESH K LProject Manager, PMP| Bharat Electronics, Bengaluru, IndiaBengaluru, Karnataka, India
Hi Pruthvi, Create Milestone(s) in MPP with duration as 0 days. Saving Changes...
By default, tasks with 0 days duration are identified as milestones, but you can also manually set the milestone flag on tasks if you wish them to appear in that report.
I have set the duration of milestone to 0. Even then the milestone report is blank. But when I try to generate the report in a different project, I am able to view the report. It is something strange.
Regards,
Pruthviu
...
2 replies by Kiron Bondale and SEAN O REILLY
Jul 19, 2018 11:54 AM
Kiron Bondale
...
Have you checked whether the milestone checkbox is ticked in the details dialog box.
Kiron
Aug 04, 2020 11:56 AM
SEAN O REILLY
...
Same issue, I never got t o the bottom of it. Did you find a solution?
In the milestone report, for each table, click on the Name field. This will open the Field List panel on the side of the screen. toward the bottom of the Tasks tab in the Field List panel, select "Show Hierarchy". Saving Changes...
I have set the duration of milestone to 0. Even then the milestone report is blank. But when I try to generate the report in a different project, I am able to view the report. It is something strange.
Regards,
Pruthviu
Have you checked whether the milestone checkbox is ticked in the details dialog box.
Kiron Saving Changes...
SEAN O REILLYProgram Manager| MERIT MEDICALOranmore, Galway, Ireland
Jul 19, 2018 9:19 AM
Replying to Pruthvi Srinath Kumbargeri
...
Hi Kyriakos, Rajesh & Kiron,
I have set the duration of milestone to 0. Even then the milestone report is blank. But when I try to generate the report in a different project, I am able to view the report. It is something strange.
Regards,
Pruthviu
Same issue, I never got t o the bottom of it. Did you find a solution? Saving Changes...
Sergio Luis ConteHelping to create solutions for everyone| Worldwide based OrganizationsBuenos Aires, Argentina
Mark the task/activity as milestone. Zero duration is not enough. I think @Kron above wrote the same. Saving Changes...