What formula to use to calculate # of project team for executing project activities?

linkedin twitter facebook   Estimating  
avatar
Riyadh Salih Saskatchewan, Canada
calculating headcount is important to based on full-time equivalent considering which contractors and temp. employees to be included in the calculations.
shall we come up with a ration in dollar amount?
Sort By:
< 1 2 >
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Riyadh -

Is your question regarding how to estimate your total resource costs or rather how to determine the optimal sized team to deliver the work by a given date?

If the former, then that should be an outcome of estimating your individual resource requirements at the activity level and aggregating those, but if it is the latter then that is the more complex analysis of developing a schedule and then optimizing it balancing optimal time size against due dates and availability of skilled resources...

Kiron
avatar
Riyadh Salih Saskatchewan, Canada
Kiron, thanks for your feedback and salute to your intelligence yeah I was looking for second one I did not find any formula in pmbok guide to quantify cost of project assets replacement executed by team headcount or to benchmark cost of individual activity per number of executing head cost
I believe such calculations help to compare with other projects
avatar
Riyadh Salih Saskatchewan, Canada
Kiron, do you have any reference in the PMBOK guide accordingly
...
1 reply by Rami Kaibni
Jul 21, 2018 12:25 AM
Rami Kaibni
...
It is in the Schedule Management Chapter under Estimate Activity Resources
avatar
Kevin Drake Perth, Western Australia, Australia
I wonder if there is another method to calculate that
...
1 reply by Riyadh Salih
Jul 22, 2018 3:45 AM
Riyadh Salih
...
Kevin, yes there is
avatar
RAJESH K L Project Manager, PMP| Bharat Electronics, Bengaluru, India Bengaluru, Karnataka, India
For software based project, there is a formula to find FTE based on KLOC and duration of project
...
1 reply by Riyadh Salih
Jul 22, 2018 3:46 AM
Riyadh Salih
...
Rajesh, that's the one FTE I am using, thanks for feedback
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Jul 20, 2018 8:03 PM
Replying to Riyadh Salih
...
Kiron, do you have any reference in the PMBOK guide accordingly
It is in the Schedule Management Chapter under Estimate Activity Resources
...
1 reply by Riyadh Salih
Jul 22, 2018 3:46 AM
Riyadh Salih
...
Thanks Rami
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Estimate Activity Resources has now moved from the Time Management chapter in PMBOK 5 to the Resource Management chapter in PMBOK 6. I get confused between the two sometimes. Anyway it's on page 320.
...
1 reply by Riyadh Salih
Jul 22, 2018 3:48 AM
Riyadh Salih
...
Sante, thanks for your page reference but I could not find much details for the formula of FTE.
avatar
Riyadh Salih Saskatchewan, Canada
Jul 20, 2018 9:42 PM
Replying to Kevin Drake
...
I wonder if there is another method to calculate that
Kevin, yes there is
avatar
Riyadh Salih Saskatchewan, Canada
Jul 21, 2018 12:25 AM
Replying to Rami Kaibni
...
It is in the Schedule Management Chapter under Estimate Activity Resources
Thanks Rami
avatar
Riyadh Salih Saskatchewan, Canada
Jul 20, 2018 10:48 PM
Replying to RAJESH K L
...
For software based project, there is a formula to find FTE based on KLOC and duration of project
Rajesh, that's the one FTE I am using, thanks for feedback