Damian PereraMonitoring & Evaluation Specialist| ChrysalisMellawagedara, Western Province, Sri Lanka
Scope creep is one of the major reasons behind project faliure. Causes of scope creep may differ from one industry to another. What are the most common causes of scope creep in your industry? Saving Changes...
Eric SimmsSenior Program ManagerBaltimore, Maryland, United States
I work primarily in the Information Technology industry, and in my experience scope creep is caused by:
1. Poorly defined project goals and expected outcomes (often because no one bothered to create a project charter)
2. Poor communication between the project manager and stakeholders, resulting in each stakeholder having a different expectation of the project outcome
3. Project Managers who lack the courage to resist customers who intentionally try to expand the project scope Saving Changes...
A lack of understanding what is really needed on the part of the customer combined with an aggressive stance on nailing down all requirements prematurely by the project team.
Kiron Saving Changes...
Justus NScrum Master| BCBSTXArlington, Tx, United States
Lack of clear goals and vague requirements Saving Changes...
Hi. Here are few causes which caused scope creep in software development projects
- No prioritization of requirements
- management agrees to everything customer asks for
- trying to exceed customer satisfaction
- lack of proper change control
- lack of project planning
- and no clarity in vision/objective of the project when it was initiated. Saving Changes...
Dinah YoungProject Manager / Software Asset Manager| Prince William CountySpringfield, Va, United States
I agree with what others have said:
- Requirements are not clearly or completely defined
- Stakeholder management not being done
- Missed stakeholders when gathering requirements
- Lack of interest of resistance from stakeholders
- Rush to start development and poor planning as a result
- Change control not implemented and not explained to or adopted by the stakeholders
- The definition of "done" was not set Saving Changes...
Senior Projects Manager | Field & Marten AssociatesNew Westminster, British Columbia, Canada
- Weak WBS
- Ambigious Scope Statement and Baseline
- Unclear Project Vision
- Lack of Communication
- Lack of CCB Saving Changes...
Anita DhirPresident/CEO| Medhira EnterprisesLong Island City, Ny, United States
PM's inability to say no / not use the change management process. Saving Changes...
Tamer Zeyad SadiqAssistant Cost Manager| Turner & TownsendRiyadh, Ar Riyad, Saudi Arabia
Many reasons like: not all stakeholders were identified, not all requirements were gathered as well to define scope, not follow communication management plan and stakeholders, lack knowledge of project management plan...etc