Change requests approval by Project Manager

linkedin twitter facebook   Change Management  
avatar
Moloy Chakraborty Principal Project Manager| WSP UK LTD High Wycombe, Buckinghamshire, United Kingdom
When project manager approve or reject the change requests?
Sort By:
< 1 2 >
avatar
MANSOUR THABET ALQUBATY System Controller| Teleyemen Sana'A, N/A, Yemen
Impact analysis done by PM and his team.
(it is a very important step before Approval/Reject)
("Change request approval by project manager" is defined in the change management plan then he can do approval/reject)

OR by

An authority within the project management team or external organization.
(is it a definition or near by for CCB- Change Control Board Commitee) who is responsible
for Approval/Reject.

BR,
Mansour
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Moloy -

As Mansour indicates, the Change Management Plan should provide the procedures and approval authorities, but often times this is dictated by organizational policy.

Kiron
avatar
Jesus Martheyn Project Manager SR Lvl 2| Globant Medellin, Antioquia, Colombia
Hi Moloy,

Well, according with PMBOK, it should be indicated on the Project Management Plan, where is stablished how is the change management approached.As Kiron Says, it should be indicated on the Change Management Plan. In my experience, most of changes are approved by sponsors, but again, you should check your PM Plan or CM plan.
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Well theoretically when it's outside scope for waterfall projects, or can't fit within a fixed time/budget in Agile projects.
avatar
Muthukrishnan Ramakrishnan Automation & Validation Engineer| Automation & Validation Solutions Taichung, Taichung, Taiwan
From my understanding, it depends on the organisational policy
avatar
RAJESH K L Project Manager, PMP| Bharat Electronics, Bengaluru, India Bengaluru, Karnataka, India
Agree with Kiron & Mansoor
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Never. The only responsability from project management perspective is to manage all activities defined inside the project change mangement process to create de needed information to put it on hands of people that must decide about the change.
avatar
Srikana Ray
Community Champion
IT Project Manager
Typically in IT Software Change management process is handled and managed by Project Manager and never approved by PM. There will be board or panel consisting of mostly senior management and Business Lead/team who would approve or deny the Change request.
avatar
Eduard Hernandez
Community Champion
Product Operations Program Manager Barcelona, Cataluña, Spain
Never, at the most the PM may give an advise or recommendation to the decision makers.
avatar
Tamer Zeyad Sadiq Assistant Cost Manager| Turner & Townsend Riyadh, Ar Riyad, Saudi Arabia
Change Control Board (CCB) and PM is a part from this board to approve or reject or delay any CR!!