Which of the following is not provided by the framework of a Work Breakdown Structure?
a. All tasks to be performed can be identified and resources allocated to them b. Once resource levels have been allocated to tasks, estimates of task duration can be made c. A network diagram, illustrating task dependencies, can be constructed d. All cost and resource allocations can be totaled to develop the overall project Budget Saving Changes...
Sort By:
Kingsley OnuohaLong Range Project Controls Specialist| Center Point EnergyRichmond, Tx, United States
Senior Projects Manager | Field & Marten AssociatesNew Westminster, British Columbia, Canada
Of course it is C ! Network diagram is not part of the WBS but WBS is an essential input for creating the Network Diagram. Saving Changes...
Moloy ChakrabortyPrincipal Project Manager| WSP UK LTDHigh Wycombe, Buckinghamshire, United Kingdom
using the WBS we can identify the tasks to be performed, estimate the resources and cost. But for creating a network diagram we require a list of activities which is not part of WBS
Hence the correct answer is ''A network diagram, illustrating task dependencies, can be constructed'' Saving Changes...