WBS

linkedin twitter facebook   Work Breakdown Structures (WBS)  
avatar
Muthukrishnan Ramakrishnan Automation & Validation Engineer| Automation & Validation Solutions Taichung, Taichung, Taiwan
Understood what is WBS? But not sure when these are prepared? Is it done before project commencement or during project?
Sort By:
avatar
Drake Settsu Project Manager / Blogger Hi, United States
You prepare it before you start the project using all the information you know at the time. You also do it when new requirements get added to a project in progress.
avatar
Stanley Oranika Director Finance & Strategy| Virtus Deus F.C.T, Abuja, Nigeria
Dear Mr Ramakrishnan,

The WBS brings about outputs called, the Scope Baseline and Project Documents Updates. Create WBS falls under the Project Scope Management knowledge area, within the Planning process group.

Components of the Scope Baseline include the WBS and the WBS dictionary. The painstaking processes of decomposition and consulting for expert judgement are tools and techniques used in reaching this goal.

Usually, a WBS is created after project scope has been defined, using the Project Scope Statement as an input.

This means that a charter has been signed and the project has commenced. In a nutshell, WBS is created during the planning phase of the project.
avatar
Drew Craig Sr. Agile & Product Coach| Vanguard Philadelphia, Pa, United States
Not much more to add from Stanley's comment.
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
My recommendation, beyond valuable comments above, is going to the WBS standard and PMI related standards like the PMBOK
avatar
Muhammad Usman Iqbal Malik Project Manager|Engineering Design and Development Lahore, Pakistan
Key aspect in creating WBS is the "team involvement". When the team gets involved in creating WBS during planning phase of the project, outcomes in the execution phase become more valid and "as desired".
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Muthukrishnan -

While a WBS is a key input into your scope baseline, like most other key project management artifacts, it is a living document and can change as a result of project scope changes but also if one is following a progressive elaboration approach.

Kiron
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Muthukrishnan, you can also learn more by downloading (if you are a PMI member) the Practice Standard for WBS:

https://www.pmi.org/pmbok-guide-standards/...res-2nd-edition
avatar
Tamer Zeyad Sadiq Assistant Cost Manager| Turner & Townsend Riyadh, Ar Riyad, Saudi Arabia
As Kiron said WBS is a key of any baseline and progressive management plan in any knowledge!!!
avatar
RAJESH K L Project Manager, PMP| Bharat Electronics, Bengaluru, India Bengaluru, Karnataka, India
Agree with Stanley
avatar
AZAD KUMAR Manager| KEI Industries Limited Faridabad, Haryana, India
the WBS is the first step of the planning process after scope of project is determined.

Please login or join to reply