Project or Phase Closing

linkedin twitter facebook   Estimating   Governance  
avatar
Elizeu Antonio Manager for Network Operations| MSTelcom Luanda, Angola
How many times you perform "Close Project or Phase" process when a certain project has four phases defined?

It is my understanding that I will perform this process five times, i.e., once at the end of each phase and once for the whole project.

Thank you in advance for your comments.
Sort By:
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Elizeu -

In the case of the final phase, the activities and deliverables might be consolidated as part of project closure, so you could end up with only four passes through that process...

Kiron
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Just to add some information, for example in my actual work place, we have a Tier clasification of projects: from Tier 1 to Tier 5. Tier 1 are the most critical ones. Depending of the Tier clasification is the steps of our governance process we need to follow.
...
1 reply by Kiron Bondale
Dec 16, 2018 11:19 AM
Kiron Bondale
...
Sergio -

Not directly related to the original question, but I'm interested in knowing how your current organization is structuring their tiers. I'm assuming it is based on estimated project cost, so what are the thresholds they are using?

My current client (and former employer) also has a five tier classification model hence my interest in learning whether the thresholds are the same. Our lowest tier was $250,000 and was recently raised to $0.5 Million, and the highest tier starts at $50 Million...

Kiron
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Yes you may perform the close function as part of a phase or project, which is why it is called just that, but in your example the actually process would normally be four times with additional tasks in the final close.
avatar
Joao Sarmento Senior Project/Program Manager| UNITEL Luanda, Luanda, Angola
Hi Elizeu. Usually the last close phase and the close project are bundled together, since some of the activities are common and refer to the project as a whole.
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Nov 06, 2018 9:25 AM
Replying to Sergio Luis Conte
...
Just to add some information, for example in my actual work place, we have a Tier clasification of projects: from Tier 1 to Tier 5. Tier 1 are the most critical ones. Depending of the Tier clasification is the steps of our governance process we need to follow.
Sergio -

Not directly related to the original question, but I'm interested in knowing how your current organization is structuring their tiers. I'm assuming it is based on estimated project cost, so what are the thresholds they are using?

My current client (and former employer) also has a five tier classification model hence my interest in learning whether the thresholds are the same. Our lowest tier was $250,000 and was recently raised to $0.5 Million, and the highest tier starts at $50 Million...

Kiron
...
1 reply by Sergio Luis Conte
Dec 16, 2018 4:28 PM
Sergio Luis Conte
...
We have an excell spreadsheet where cost is only one of the questions that contribute to calculate the tier. Tier and risk is related in our case but cost is not the most important factor.
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Dec 16, 2018 11:19 AM
Replying to Kiron Bondale
...
Sergio -

Not directly related to the original question, but I'm interested in knowing how your current organization is structuring their tiers. I'm assuming it is based on estimated project cost, so what are the thresholds they are using?

My current client (and former employer) also has a five tier classification model hence my interest in learning whether the thresholds are the same. Our lowest tier was $250,000 and was recently raised to $0.5 Million, and the highest tier starts at $50 Million...

Kiron
We have an excell spreadsheet where cost is only one of the questions that contribute to calculate the tier. Tier and risk is related in our case but cost is not the most important factor.
avatar
RAJESH K L Project Manager, PMP| Bharat Electronics, Bengaluru, India Bengaluru, Karnataka, India
Agree with Joao.