I'm looking for a shared perspective on the following:
On a Scrum framework, where estimations are done using the Fibonacci sequence to measure complexity of each task/issue, how can we develop a sense of comparison between the complexity and the time it actually takes?
It is easy to face both tasks evaluated with a 3 (low complexity task) taking 2 months to fully complete as well as others graded with a 13 that somehow are managed in one or two sprints. Is there any way to establish a time-tracker / time comparison that helps a team to develop a better sense of commitment in the delivery and a better notion on how to estimate properly?
Also, I'm now learning more about Software Development metrics using Kanban and Scrum. Would you mind sharing your experiences?