How do you manage risks in an agile environment?

linkedin twitter facebook   Agile   Risk Management  
avatar
Mario Coquillat Project, Program and Portfolio consultant, mentor and trainer| CoquillatPM San Pedro Del Pinatar, Murcia, Spain
Some practitioners consider that agile manage risks implicitly through a variety of practices (Continuous Delivery, Automated Testing, short iterations).

Other practitioners consider necessary to manage risks explicitly using practices as Spikes, ROAM and Risk Breakdown Chart.

Your insights would be much appreciated.
Sort By:
< 1 2 >
avatar
Angel Najera Perez CEO| WOLF PROJECT MANAGEMENT, S.L. Alicante, Spain
I consider that the best approach in agile is to work with the kanban board including risk (or the different response plans -activities- to be done in order to attack them). So that the team can visualize and priotize them, exactly the same as any other user story.
On the other hand, I also think that having a risk register where the risks can be handed propertly is mandatory.
avatar
Mario Coquillat Project, Program and Portfolio consultant, mentor and trainer| CoquillatPM San Pedro Del Pinatar, Murcia, Spain
Thanks Angel

So you´re talking about a hybrid approach, both in Kanban (agile) and risk register (predictive). That´s a good point.
avatar
Mohammed Alotaibi Jubail, 04, Saudi Arabia
Thanks for all
avatar
Latha Thamma reddi Sr Product and Portfolio Management (Automation Innovation)| DXC Technology Mckinney, Tx, United States
Thank You!.
< 1 2 >

Please login or join to reply