Project Management

Please login or join to subscribe to this thread

What will be the best way to implement change management in Construction Field?.

linkedin twitter facebook   Change Management  
avatar
Juher Pathan Surat, Gujarat, India
I need to understand best change management practices in Construction Management.
Sort By:
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
I'd look to Rami, Riyadh or one of the other practitioners who have experience in that domain to provide specific practices, but I'd say the basic principles of the ADKAR model (individual-focused) combined with Kotter's teachings (e.g. create a sense of urgency) should apply.

Given the vast number of influencing stakeholders on large construction projects, early and regular engagement is probably a good idea!

Kiron
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Juher,

Change management on construction projects isn’t any different from the process in any other industry. In principal:

- CM issues an RFI (Request for Information) or TQ (Technical Query)
- Concerned Design Consultant reviews it and responds to the RFI or TQ and when a change is required due to design discrepancy or missing items o nether drawings, they issue an SI (Site Instruction).
- The CM reviews the SI, then issues a report along with a change order, if necessary, to the client or owner.
- Then owner’s / project building committee reviews the change order, assess all impact illustrated by the CM and either Approves or Requests further clarifications if various options are involved.

There are many types of change orders. Those due to missing design items, or unforeseen issues on site which we call force majeure, changes requested directly by the client, changes requested to to change in circumstances or market demand but the process for all of those in principal is the same and all of them have to go through a proper change order process.

Hope this helps !
...
2 replies by Juher Pathan
Jan 22, 2019 6:46 AM
Juher Pathan
...
Thank for your valuable guidance.
Jan 22, 2019 6:47 AM
Juher Pathan
...
Thank you very much for guidance and clarification.
avatar
Tamer Zeyad Sadiq Assistant Cost Manager| Turner & Townsend Riyadh, Ar Riyad, Saudi Arabia
Well you should know the change management process well. Then, you should know what contract clauses and company policy and formats and understand your company procedures how to make change request. After that, as Rami said you should have approval documents and submittal as evidence to change any issue in a proper way!!!
avatar
Juher Pathan Surat, Gujarat, India
Jan 19, 2019 4:31 PM
Replying to Rami Kaibni
...
Juher,

Change management on construction projects isn’t any different from the process in any other industry. In principal:

- CM issues an RFI (Request for Information) or TQ (Technical Query)
- Concerned Design Consultant reviews it and responds to the RFI or TQ and when a change is required due to design discrepancy or missing items o nether drawings, they issue an SI (Site Instruction).
- The CM reviews the SI, then issues a report along with a change order, if necessary, to the client or owner.
- Then owner’s / project building committee reviews the change order, assess all impact illustrated by the CM and either Approves or Requests further clarifications if various options are involved.

There are many types of change orders. Those due to missing design items, or unforeseen issues on site which we call force majeure, changes requested directly by the client, changes requested to to change in circumstances or market demand but the process for all of those in principal is the same and all of them have to go through a proper change order process.

Hope this helps !
Thank for your valuable guidance.
avatar
Juher Pathan Surat, Gujarat, India
Jan 19, 2019 4:31 PM
Replying to Rami Kaibni
...
Juher,

Change management on construction projects isn’t any different from the process in any other industry. In principal:

- CM issues an RFI (Request for Information) or TQ (Technical Query)
- Concerned Design Consultant reviews it and responds to the RFI or TQ and when a change is required due to design discrepancy or missing items o nether drawings, they issue an SI (Site Instruction).
- The CM reviews the SI, then issues a report along with a change order, if necessary, to the client or owner.
- Then owner’s / project building committee reviews the change order, assess all impact illustrated by the CM and either Approves or Requests further clarifications if various options are involved.

There are many types of change orders. Those due to missing design items, or unforeseen issues on site which we call force majeure, changes requested directly by the client, changes requested to to change in circumstances or market demand but the process for all of those in principal is the same and all of them have to go through a proper change order process.

Hope this helps !
Thank you very much for guidance and clarification.
In a construction, the term 'change management' can sometimes be used to refer to change control processes where changes to a project’s scope – which may have impacts on time, cost or quality – are assessed and approved. A request for information (RFI) is a standard business process whose purpose is to collect written information about the capabilities of various suppliers. Normally it follows a format that can be used for comparative purposes.

Organisations can go through periods of significant change during construction projects. There may be need to:

Redefine business operations during the preparation of a project brief.
Re-structure the business organisation.
Move the location of the business, which can entail moving house, moving children to a new school, moving partners and so on.

Reference: https://www.projectcubicle.com/request-for...on-rfi-process/

Please login or join to reply

Content ID:
ADVERTISEMENTS

"I choose a block of marble and chop off whatever I don't need."

- Rodin

ADVERTISEMENT

Sponsors