E2E delivery

linkedin twitter facebook   Agile  
avatar
Milind Patil Bangalore, Karnataka, India
I often read this in PM JD that PM should be responsible for E2E project delivery

What exactly is it? Who are the actors?
What are the key deliverable PM has to focus on?
Does it has a time limit? I mean when it ends.
Sort By:
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
First question is: what does mean E2E? it could be lot of things.
...
1 reply by Milind Patil
Jan 26, 2019 1:11 PM
Milind Patil
...
Sergio

End to End project management and delivery.
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
In its simplest translation, E2E would mean the PM is accountable for project delivery from the official start of the project till final closeout. This is one of those generalizations in job descriptions that doesn't really offer much insights - for example, it doesn't tell you what level of authority the PM will be vested with or what specific activities the PM is expected to perform.

Kiron
...
1 reply by Milind Patil
Jan 26, 2019 1:12 PM
Milind Patil
...
Thanks.
avatar
Milind Patil Bangalore, Karnataka, India
Jan 26, 2019 6:32 AM
Replying to Sergio Luis Conte
...
First question is: what does mean E2E? it could be lot of things.
Sergio

End to End project management and delivery.
...
1 reply by Sergio Luis Conte
Jan 26, 2019 3:30 PM
Sergio Luis Conte
...
Thanks.Project delivery does not exists. Organizations are not delivering projects. Organizations are running projects to deliver solutions. Solution is equal to "the thing" to be created (product/service/result) plus "the process" to create it (project). Project Manger is accountable for the process while Business Analyst is accountable for all before the project and all after the project while during the project she/he is actively working on all related to assure that the defined product/service/result is created as defined. Key here is to define the solution scope. For example, some methods like PRNCE2 includes all related to pre-project activities and some post-project activities while some guidelines like PMBOK does not includes that.
avatar
Milind Patil Bangalore, Karnataka, India
Jan 26, 2019 7:46 AM
Replying to Kiron Bondale
...
In its simplest translation, E2E would mean the PM is accountable for project delivery from the official start of the project till final closeout. This is one of those generalizations in job descriptions that doesn't really offer much insights - for example, it doesn't tell you what level of authority the PM will be vested with or what specific activities the PM is expected to perform.

Kiron
Thanks.
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Jan 26, 2019 1:11 PM
Replying to Milind Patil
...
Sergio

End to End project management and delivery.
Thanks.Project delivery does not exists. Organizations are not delivering projects. Organizations are running projects to deliver solutions. Solution is equal to "the thing" to be created (product/service/result) plus "the process" to create it (project). Project Manger is accountable for the process while Business Analyst is accountable for all before the project and all after the project while during the project she/he is actively working on all related to assure that the defined product/service/result is created as defined. Key here is to define the solution scope. For example, some methods like PRNCE2 includes all related to pre-project activities and some post-project activities while some guidelines like PMBOK does not includes that.

Please login or join to reply

Content ID:
ADVERTISEMENTS

A celebrity is a person who works hard all his life to become known, then wears dark glasses to avoid being recognized.

- Fred Allen

ADVERTISEMENT

Sponsors