Is there a deliverable called risk response plan?
Which document should we refer to find out the risk response to be implemented? Saving Changes...
Sort By:
Sergio Luis ConteHelping to create solutions for everyone| Worldwide based OrganizationsBuenos Aires, Argentina
In my personal experience we use the risk register to put the response plan inside it. Obviously the risk response plan could generate other documents and in fact a parallel project too. Saving Changes...
Tamer Zeyad SadiqAssistant Cost Manager| Turner & TownsendRiyadh, Ar Riyad, Saudi Arabia
As per PMBOK, the risk register should contain risk response list Saving Changes...
Basic risk responses are captured in the risk register but the "footprint" of a risk response might be seen in many other PM documents including the WBS & schedule or budget.
"Far out in the uncharted backwaters of the unfashionable end of the Western Spiral arm of the galaxy lies a small unregarded yellow sun. Orbiting this at a distance of roughly 98 million miles is an utterly insignificant little blue-green planet whose ape-descended life forms are so amazingly primitive that they still think digital watches are a pretty neat idea..."