EEF Vs External Dependency.

linkedin twitter facebook   Schedule Management   Scheduling  
avatar
Lenin Anbalagan Dharmapuri, Tamil Nadu, India
I feel not clear with the dependencies detailed in pmbok while sequence activities process. Can i say EEF is also same as external dependencies since non project activities?
Sort By:
avatar
Thomas Walenta Global Project Economy Expert Hackenheim, Germany
EEFs rather are constraints for modelling your project while external dependencies are dependencies between project activities and outside activities, mostly represented by milestones in the schedule.

Examples for external dependencies are if you have to wait for another project to create a deliverable you need as input for project work (a crane to be erected by a subcontractor for building a house) or deliverables your project produces that are needed by others at a specific time (like Olympic games preparation - building a stadium).

EEFs are described in the PMBoK in length.
...
1 reply by Lenin Anbalagan
Apr 14, 2019 5:51 AM
Lenin Anbalagan
...
Thank you Mr.Thomas.. Perfect
avatar
Lenin Anbalagan Dharmapuri, Tamil Nadu, India
Apr 12, 2019 9:41 AM
Replying to Thomas Walenta
...
EEFs rather are constraints for modelling your project while external dependencies are dependencies between project activities and outside activities, mostly represented by milestones in the schedule.

Examples for external dependencies are if you have to wait for another project to create a deliverable you need as input for project work (a crane to be erected by a subcontractor for building a house) or deliverables your project produces that are needed by others at a specific time (like Olympic games preparation - building a stadium).

EEFs are described in the PMBoK in length.
Thank you Mr.Thomas.. Perfect