Why does Control Scope does not have Risk Register as an Output?

linkedin twitter facebook  
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
Just as most other control processes why does Control Scope does not have Risk Register as an Output?

If Control Schedule has Risk Register as an updated document
If Control Costs has Risk Register as an updated document
If Control Risks has Risk Register as an updated document
If Quality Control has Risk Register as an updated document
If Monitor and Control Project Work has Risk Register as an updated document
If Control Procurements has Risk Register as an updated document
If Control Resources has Risk Register as an updated document
If Monitor Stakeholder Engagement has Risk Register as an updated document

Why Scope Control does NOT have Risk Register as an updated document
Sort By:
< 1 2 >
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
This is strange for me...
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
George -

Updates to the risk register are only made through the RM processes. As such, in the process of monitoring scope or any other M&C type process, the team might iterate back through identifying and analyzing risks resulting in updates to the register.

Kiron
...
1 reply by George Lewis
Apr 22, 2019 7:04 PM
George Lewis
...
Kiron - what's RM processes?
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
Apr 22, 2019 6:47 PM
Replying to Kiron Bondale
...
George -

Updates to the risk register are only made through the RM processes. As such, in the process of monitoring scope or any other M&C type process, the team might iterate back through identifying and analyzing risks resulting in updates to the register.

Kiron
Kiron - what's RM processes?
...
1 reply by Gordon Alexander
Apr 22, 2019 8:36 PM
Gordon Alexander
...
Risk Management
avatar
Gordon Alexander Senior Principal - Global Programme Director| Indepndent Chelmsford, Essex, United Kingdom
Apr 22, 2019 7:04 PM
Replying to George Lewis
...
Kiron - what's RM processes?
Risk Management
avatar
Gordon Alexander Senior Principal - Global Programme Director| Indepndent Chelmsford, Essex, United Kingdom
Hi George,

Monitor Scope means monitoring Risk, change, dependency etc for anything that might change the scope of the project/prog. The risk register is something that is monitored and not an output of that process, but is as Kiron says part of the Risk management process.
avatar
Keith Novak Tukwila, Wa, United States
The words Monitor Scope do not appear together anywhere in the PMBoK.
...
1 reply by George Lewis
Apr 23, 2019 12:19 AM
George Lewis
...
Keith - you're right, please read Control Scope... thanks for the catch.

Maybe you can now try giving a logical answer :)
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
Kiron, thanks for your reply but Risk Register is listed as outputs of 18 Processes, 22 if you include the 4 Risk Management processes where it's listed as an output... (the count could be wrong, some can give the exact count if want to :) )

But what's definitely not wrong is that Risk Register is listed as an output of 8 of the Monitor and Control processes as Project Document Updates...
Schedule
Cost
Risk
Quality
Integration
Procurements
Resources
Stakeholder


All Monitoring and Control except Monitor Communication and Control Scope.

Someone must be able to give a logical thought of this...
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
Apr 22, 2019 9:40 PM
Replying to Keith Novak
...
The words Monitor Scope do not appear together anywhere in the PMBoK.
Keith - you're right, please read Control Scope... thanks for the catch.

Maybe you can now try giving a logical answer :)
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
Hope someone can help me with an logical explanation...
avatar
Tarik Chougua Project Manager| CEPEO Ottawa, Ontario, Canada
Good question. I'm interested in the response too if someone can help.
< 1 2 >

Please login or join to reply