Riad AlhammoudProject management| LanganAbu Dhabi, United Arab Emirates
Dears,
Kindly could you share your experience with variation order process from the the beginning ( change request) and until the final (receipt of final payment). Saving Changes...
Stéphane ParentSelf Employed / Semi-retired| Leader MakerPrince Edward Island, Canada
1. Identify/capture change request
2. Provide rough order of magnitude (ROM) estimate for change request and level of effort (LOE) for impact analysis
3. GATE: Decide whether to proceed with impact analysis
4. Provide impact analysis, LOE and cost for change request
5: GATE: Decide whether to proceed with change request
6. If approved, integrate change request into project scope, budget and schedule
7. Invoice change request when completed. Saving Changes...