You can consider the following:
If the material procured is part of the project, you could distribute the material cost to the duration of the project. For e.g. software license procured for a particular project is $1000, and if the duration if the project is 10 months. You can load the cost evenly as $100 per month for 10 months. If the material is used for multiple projects you could distribute the cost accordingly between projects. This way you will not load the cost upfront to skew the calculations. If the material procured is a capex, then the cost gets tracked elsewhere not in EVM. Hope this will help.