An interesting project management question...

linkedin twitter facebook   Estimating  
avatar
Eddy Merlinhouse Oh, United States
It's a hypothetical so bear with me,...You're building a house with ten parallel tasks that each take on average six months to perform.

So what is the chance that the project will take six months?

Thanks,
https://diceus.com/dedicated-development-team-for-your-advantage/
Sort By:
< 1 2 >
avatar
Abolfazl Yousefi Darestani Manager, Quality and Continuous Improvement| Hörmann-TNR Industrial Doors Newmarket, Ontario, Canada
Agree with Sergio.
avatar
Daire Guiney Dublin, Dublin, Ireland
The outcome of this project is based on the amount of available resources. You could hire 10 project managers responsible for one of the ten parallel tasks. As long as the tasks are not interdependent upon one another then it is possible to finish the project within the six month time frame. Also the term on average is used for completion of the parallel tasks and thus could be complete before the six months so it is again possible to complete the project within the six month time frame