Riad AlhammoudProject management| LanganAbu Dhabi, United Arab Emirates
What should be your action as project manager when you heard from your team that the contractor damaged some utilities on site when executing activities.
Will be better to give a warning and follow what contract states or ask the contractor to explain what went wrong and ensure this will not be repeated. Saving Changes...
Sort By:
Paul AzanorProject Consultant| Lagos NigeriaIkoyi, Lagos, Nigeria
If there is such a clause in contract, you may want to invoke same for whatever penalties otherwise you may just let go. In any case there has to be an incident report to determine the root cause. Saving Changes...
It depends on the magnitude of the incident, its impact to the organization and your project, your organization's procurement policies and the terms & conditions in the contract.
For example, some contracts might require the contractor to carry sufficient insurance to cover such mishaps in which case your vendor management team might choose to file a claim.
Kiron Saving Changes...
Sergio Luis ConteHelping to create solutions for everyone| Worldwide based OrganizationsBuenos Aires, Argentina
What does mean "the contractor damaged some utilities on site when executing activities"? Saving Changes...
Priya PatraDelivery Director| Capgemini India Technology Services LtdMumbai, India
We usually follow the contract. I am from IT industry and we work as contractors for our customers, we are governed by the contract, if there is a breach, sometimes we have pay penalties. Saving Changes...
Stéphane ParentSelf Employed / Semi-retired| Leader MakerPrince Edward Island, Canada
We follow the golden rule: "The client has the gold. The client makes the rules." Saving Changes...
Eric IsomOwner| learn.pmguaranteed.comUt, United States
Why not do both? Saving Changes...
SANDEEP KUMAR MISHRAProject Manager-Planning & ManagementNew Delhi, Delhi, India
If contract clause says, we will give them a written warning with proof just after the incident to rectify the issue. Also, a notice to them by keeping our prejudice for recovery of loss from his payment.
Post work, we can settle the payment with reference to above mentioned warning and notice. Everybody will get time to estimate the damage and work completion. Saving Changes...
"You can make more friends in two months by becoming interested in other people than you can in two years by trying to get other people interested in you."