How many times is a project charter created in the project?

linkedin twitter facebook  
avatar
Thomas Walenta Global Project Economy Expert Hackenheim, Germany
In PMBoK 4.1 this question is answered as 'once or at predefined points in the project'.

I personally have never seen a charter that was changed during a project. When the need for a change came up, it was handled thru change request. I see the project charter as a birth certificate. There might have been charters for phases, these are not project charters though.

What is your experience?
Sort By:
< 1 2 3 >
avatar
Raj Shekhar Bidika Maintenance Engineer| Reliance Industries Limited Jamnagar, Gujarat, India
Once, unless there is a major change which heavily impacts the project deliverables and objectives.