How many times is a project charter created in the project?
Thomas WalentaGlobal Project Economy ExpertHackenheim, Germany
In PMBoK 4.1 this question is answered as 'once or at predefined points in the project'.
I personally have never seen a charter that was changed during a project. When the need for a change came up, it was handled thru change request. I see the project charter as a birth certificate. There might have been charters for phases, these are not project charters though.