Alexandre CostaScrum Master| Integer Consulting - Pictet technologiesLoures, Portugal
In project management, a critical path is the sequence of project network activities which add up to the longest overall duration, regardless if that longest duration has float or not. This determines the shortest time possible to complete the project.
...
1 reply by praveen nakkina
Sep 17, 2019 4:00 PM
praveen nakkina
...
Thank for your reply and time .But my question is still unanswered as I want to know why critical path is considered be shortest time even though it has longest duration estimates
In project management, a critical path is the sequence of project network activities which add up to the longest overall duration, regardless if that longest duration has float or not. This determines the shortest time possible to complete the project.
Thank for your reply and time .But my question is still unanswered as I want to know why critical path is considered be shortest time even though it has longest duration estimates
...
1 reply by Alexandre Costa
Sep 17, 2019 4:30 PM
Alexandre Costa
...
I think I was clear , my fault, you must see this from other perspective, aside from the fact has longest duration estimates, I emphasize again is the shortest time because is the shortest time in which the project can be completed no matter the duration of the critical path is the longest path, you can find other near critical paths with less duration but will not be able to complete the project.
Saving Changes...
Alexandre CostaScrum Master| Integer Consulting - Pictet technologiesLoures, Portugal
Sep 17, 2019 4:00 PM
Replying to praveen nakkina
...
Thank for your reply and time .But my question is still unanswered as I want to know why critical path is considered be shortest time even though it has longest duration estimates
I think I was clear , my fault, you must see this from other perspective, aside from the fact has longest duration estimates, I emphasize again is the shortest time because is the shortest time in which the project can be completed no matter the duration of the critical path is the longest path, you can find other near critical paths with less duration but will not be able to complete the project. Saving Changes...
Senior Projects Manager | Field & Marten AssociatesNew Westminster, British Columbia, Canada
Having the longest duration means it is the shortest time you can complete the project with. Makes sense ?
...
1 reply by praveen nakkina
Sep 18, 2019 4:34 AM
praveen nakkina
...
Sir thank you for your time and response . you are saying the same thing which i mentioned in my question. But the thing is that i want to know WHY it is considered shortest time despite of having Long Duration estimates.I just want to know WHY is this considered like this way .
Having the longest duration means it is the shortest time you can complete the project with. Makes sense ?
Sir thank you for your time and response . you are saying the same thing which i mentioned in my question. But the thing is that i want to know WHY it is considered shortest time despite of having Long Duration estimates.I just want to know WHY is this considered like this way .
...
1 reply by Rami Kaibni
Sep 18, 2019 10:22 AM
Rami Kaibni
...
I just explained to you in simple words and you can also refer to Kiron’s example. Hope it will help clear your confusion.
Longest duration refers to the path, shortest time refers to the schedule.
Saving Changes...
Karl TwortSenior Project Manager| Fresh EggUnited Kingdom
Hi Praveen,
In simple terms, if the critical path is 50 days and this is the longest duration on the project, this will be the shortest time in which the project can be delivered. Even if every other task can be completed in under 50 days, the Critical path dictates that 50 days duration is also the shortest time in which the project can be completed. Saving Changes...
The key is what shortest time refers to. It is not the shortest network path through the project but is the shortest time to complete the full project taking into account all parallel paths.
For example, if I am preparing Thanksgiving dinner and the appetizers take me 1 hour, the dessert 2 hours and the turkey four hours, the turkey cooking path is the critical path but is also representative of the shortest time (4 hours) to finish making dinner.
Senior Projects Manager | Field & Marten AssociatesNew Westminster, British Columbia, Canada
Sep 18, 2019 4:34 AM
Replying to praveen nakkina
...
Sir thank you for your time and response . you are saying the same thing which i mentioned in my question. But the thing is that i want to know WHY it is considered shortest time despite of having Long Duration estimates.I just want to know WHY is this considered like this way .
I just explained to you in simple words and you can also refer to Kiron’s example. Hope it will help clear your confusion.
Longest duration refers to the path, shortest time refers to the schedule. Saving Changes...
Mahabubur RahmanProject Manager Structures-Bridges| Department of Infrastructure, Government of Nothwest TerritoriesYellowknife, Northwest Territories, Canada
I just want to describe in a different way the same concept as described by Kiron and Rami. Actually, CP is the longest path of the network and it is the least possible time a project can be completed without impacting scope and budget. Saving Changes...
Critical path is the LONGEST path, considering sequence of activities in the schedule diagram. Thus, this LONGEST path is also the SHORTEST time the project can take, because when the activities in this path are completed, we can consider the project finished. Saving Changes...