Sep 18, 2019 7:25 AM
Replying to Kiron Bondale
...
The key is what shortest time refers to. It is not the shortest network path through the project but is the shortest time to complete the full project taking into account all parallel paths.
For example, if I am preparing Thanksgiving dinner and the appetizers take me 1 hour, the dessert 2 hours and the turkey four hours, the turkey cooking path is the critical path but is also representative of the shortest time (4 hours) to finish making dinner.
Hope that helps!
Kiron