Ok, so back in the day (2005 I believe) I started taking my one of my mpp trainings - starting with the Orange Belt. During this class, we were given several macros on a CD, and also shown how to create a formula in the Customized Fields area, specifically for showing the RAG of each task. Needless to say, I was here at work till bout 1 this morning trying to figure out the formula, and ofcourse I've been blessed with the task of fixing our org's best practices and standardizing our project plans. Not a problem, but since they now know I'm a black-belt..... you get the idea. Anyway's, I know there is a way to do this, don't know if it is by way of Macro or just creating a customized field/formula... Any help here would be greatly appreciated! Thanks everyone! Saving Changes...
Anonymous
Here's one that I keep handy for my reference. It can be used to do task level stoplights in MS Project and is also useful if setting up stoplights in Project Server