Nov 06, 2019 9:28 AM
Replying to Julie Ann Jones
...
Hi Melissa, Kamwa is correct
I hope this example will assist…. SPI = EV/PV.
SPI measures the efficiency of the schedule
EV earned value – (work performed - how much did I get done, budget cost)
PV planned value - (the ‘promise’ – how much will it cost, the budget of all work planned)
AC actual cost – (how much it actually cost in reality)
PV – the ‘promise’ was start Oct 20 and finish Oct 30 (10 days) you need the monetary value for each day, for example $100 per day = 10 days @ $100/day, therefore PV ‘promise’ is $1,000
EV – how much work did you get done by Oct 30, example 80% of $1,000 = $800
SPI = EV/PV $800/$1000 = 0.8, therefore behind schedule.
Based on the example value figures your AC would be
AC Actual Cost – how much it actually cost, Oct 20 to Nov 6 (17 days), 17 x $100 = $1,700